16437 W OTSEGO ST 91436

Certificate Information: 16437 W OTSEGO ST 91436

Application / Permit
24016-10000-12029
Plan Check / Job No.
B24LA06640
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ADU PER STATE LAW AND GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 7/8/2025
Issuing Office
Metro
Current Status
Issued on 7/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/11/2024 APPLICANT
Assigned to Plan Check Engineer 4/15/2024 ZAW HAN
Corrections Issued 4/18/2024 ZAW HAN
Building Plans Picked Up 4/23/2024 APPLICANT
Applicant returned to address corrections 9/30/2024 ALEXANDER JOO
Plan Check Approved 10/10/2024 NGHI SU
Issued 7/8/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 8/19/2024 RIDWAN HARDY
Construction within easement Cleared 8/19/2024 RIDWAN HARDY
Address approval Cleared 8/28/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/28/2024 CARLOS AGUILERA
Sewer availability Cleared 8/28/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/29/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/30/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 1/2/2026 Corrections Issued MORRIS JACKSON
Footing/Foundation/Slab 1/7/2026 Not Ready for Inspection MORRIS JACKSON
Footing/Foundation/Slab 1/13/2026 Not Ready for Inspection MORRIS JACKSON
Footing/Foundation/Slab 1/22/2026 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 2/6/2026 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 2/6/2026 Partial Approval THOMAS FINNILA
Piling/Pier/Caisson 2/6/2026 Not Ready for Inspection THOMAS FINNILA
Sewer 2/6/2026 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 2/12/2026 No Access for Inspection MORRIS JACKSON
Sewer 2/12/2026 No Access for Inspection MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 2/17/2026 Approved SEAN WIRCH
Footing/Foundation/Slab 2/17/2026 Approved SEAN WIRCH
PLUMBING-Rough 2/17/2026 Partial Approval SEAN WIRCH
Deputy Drilled-In Anchors 2/25/2026 Partial Approval SEAN WIRCH
ELECTRICAL-Rough 3/11/2026 Corrections Issued THOMAS FINNILA
HVAC-Rough 3/11/2026 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 3/11/2026 Approved THOMAS FINNILA
BUILDING-Rough-Frame 3/25/2026 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 3/25/2026 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 3/25/2026 Approved THOMAS FINNILA
MERV13>=Rough 3/25/2026 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 3/31/2026 Not Ready for Inspection MORRIS JACKSON
ELECTRICAL-Rough 3/31/2026 Approved MORRIS JACKSON
MERV13>=Rough 3/31/2026 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 4/3/2026 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 4/7/2026 Partial Approval MORRIS JACKSON
Wood Frame 4/7/2026 Not Ready for Inspection MORRIS JACKSON
Insulation 4/10/2026 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 4/14/2026 Corrections Issued ROBERT GOLD
Deputy Wood Construction 4/15/2026 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 4/20/2026 Approved JOHN KIDWELL
Drywall Nailing 4/20/2026 Approved JOHN KIDWELL
Interior/Exterior Lathing 4/20/2026 Partial Approval JOHN KIDWELL
MERV13>=Rough 4/20/2026 Approved JOHN KIDWELL
Shower Pan 4/30/2026 Approved THOMAS FINNILA
Interior/Exterior Lathing 5/7/2026 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/13/2026 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 6/1/2026 Partial Approval IVAN SARABIA
Special/Order Compliance 6/1/2026 Partial Inspection SEAN WIRCH
Underground Mechanical 6/1/2026 Corrections Issued IVAN SARABIA
ELECTRICAL-Rough 6/3/2026 Partial Approval THOMAS FINNILA
Final 6/29/2026 Not Ready for Inspection THOMAS FINNILA
Green Building Final 6/29/2026 Approved THOMAS FINNILA
MERV13>=Final 6/29/2026 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/29/2026 SGSOV No Gas THOMAS FINNILA
Smoke Detectors 6/29/2026 Corrections Issued THOMAS FINNILA