3804 N LONGVIEW VALLEY ROAD 91423
Certificate Information: 3804 N LONGVIEW VALLEY ROAD 91423
- Application / Permit
- 24016-10000-11998
- Plan Check / Job No.
- B24LA06617
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: single-story ground floor addition (carport) to (E) 1-story SFD with attached Carport
- Permit Issued
- Issued on 12/19/2024
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2024 | GEORGE JOLAKIAN |
| Corrections Issued | 5/2/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 5/21/2024 | RODOLFO ARIAS |
| Plan Check Approved | 8/15/2024 | GEORGE JOLAKIAN |
| Issued | 12/19/2024 | APPLICANT |
| CofO in Progress | 6/18/2025 | MISAEL ESPARZA |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/11/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/11/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2024 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 5/14/2024 | DALIA MOKAYED |
| Trees in Parkway | Cleared | 6/14/2024 | ADALBERTO VERA |
| Permit | Cleared | 6/25/2024 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 7/15/2024 | DALIA MOKAYED |
| Grading Pre-Inspection | Cleared | 8/15/2024 | CHARLES POWELL |
Contact Information
| Contractor | Hacienda Lopez Construction Inc; Lic. No.: 910123-B | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: NA44672 | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/23/2025 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/4/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/7/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/28/2025 | Conditional Approval | MISAEL ESPARZA |
| Green Building Rough | 2/28/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/12/2025 | Approved | MISAEL ESPARZA |
| Final | 6/12/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 6/12/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 6/12/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 6/17/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Smoke Detectors | 6/17/2025 | Approved | MISAEL ESPARZA |