3934-3934 1/2 S 2ND AVE 90008

Certificate Information: 3934-3934 1/2 S 2ND AVE 90008

Application / Permit
24016-10000-11578
Plan Check / Job No.
B24LA06324
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) ATTACHED 497 SQ FT REC ROOM INTO (N) ADU per State Law,CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 5/21/2024
Issuing Office
Current Status
CofO Issued on 5/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/10/2024 APPLICANT
Assigned to Plan Check Engineer 4/15/2024 AUNG SOE
Corrections Issued 4/17/2024 AUNG SOE
Applicant returned to address corrections 4/27/2024 KELVIN CHUONG
Plan Check Approved 5/18/2024 FERNANDO FLORES
Issued 5/21/2024 APPLICANT
CofO in Progress 5/9/2025 LUIS CASTRO
Permit Finaled 5/11/2025 DEROLD HAUFF
CofO Issued 5/11/2025 DEROLD HAUFF
Permit Finaled 5/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/23/2024 CELINA MORENO
Sewer availability Cleared 4/23/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/25/2024 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/7/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 10/16/2024 Corrections Issued ANTHONY EGSON
Gas Test 10/21/2024 Approved BARRY HACHE
PLUMBING-Rough 10/21/2024 Approved BARRY HACHE
PLUMBING-Rough 10/23/2024 Approved BARRY HACHE
HVAC-Rough 1/24/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 1/30/2025 Approved LUIS CASTRO
HVAC-Rough 1/30/2025 Corrections Issued LUIS CASTRO
BUILDING-Rough-Frame 2/3/2025 Approved LUIS CASTRO
Insulation 2/3/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 2/3/2025 Approved LUIS CASTRO
Drywall Nailing 2/12/2025 Approved LUIS CASTRO
ELECTRICAL-Final 3/13/2025 Corrections Issued LUIS CASTRO
Final 4/10/2025 Corrections Issued LUIS CASTRO
Final 5/8/2025 OK to Issue CofO LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 5/8/2025 Approved LUIS CASTRO