10345 W ROSSBURY PL 90064

Certificate Information: 10345 W ROSSBURY PL 90064

Application / Permit
24016-10000-11493
Plan Check / Job No.
B24LA06280
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW CONSTRUCTION 364 SF ADU PER GCS 65852.2(e)(1)(B) AND 12.22 A.33(c),(d) AND (g). ALL WORK PER ENG.
Permit Issued
Issued on 11/12/2024
Issuing Office
Current Status
CofO Issued on 6/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/10/2024 APPLICANT
Assigned to Plan Check Engineer 4/12/2024 LUISANGEL VALENZUELA
Corrections Issued 4/12/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/6/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 9/18/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 9/25/2024 PINANK PATEL
Applicant returned to address corrections 10/26/2024 PINANK PATEL
Plan Check Approved 11/4/2024 PINANK PATEL
Issued 11/12/2024 APPLICANT
CofO in Progress 6/5/2025 ARAM AVEDISIAN
Permit Finaled 6/10/2025 RICHARD STEINBACH
Permit Finaled 6/10/2025 RICHARD STEINBACH
CofO Issued 6/10/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/13/2024 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 5/13/2024 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/13/2024 HISASHI KOBAYAKAWA
Construction near power lines Cleared 9/10/2024 RIDWAN HARDY
Specific Plan Cleared 9/16/2024 RICHARD WOO
Grading Pre-Inspection Cleared 9/21/2024 CHARLES POWELL

Contact Information

Contractor Crane Steven & Co Inc; Lic. No.: 667129-B       ,
Engineer Perazzelli,, Joseph Ames; Lic. No.: C35270 183 GREENFIELD AVENUE      LOS ANGELES, CA 90049

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/2/2024 Partial Approval ASHLEY THOMPSON
Footing/Foundation/Slab 12/9/2024 Approved STEPHANIE SWANSON
PLUMBING-Rough 12/9/2024 Partial Approval STEPHANIE SWANSON
Underground Mechanical 12/12/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 2/25/2025 Partial Approval EVAN COOPER
ELECTRICAL-Rough 2/25/2025 Corrections Issued EVAN COOPER
Green Building Rough 2/25/2025 Not Ready for Inspection EVAN COOPER
HVAC-Rough 2/25/2025 Corrections Issued EVAN COOPER
PLUMBING-Rough 2/25/2025 Approved EVAN COOPER
Verify Sprinkler Sign Off 2/25/2025 Approved EVAN COOPER
Shower Pan 3/10/2025 Approved ASHLEY THOMPSON
Insulation 3/12/2025 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 3/12/2025 Partial Approval ASHLEY THOMPSON
Interior/Exterior Lathing 3/13/2025 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 3/18/2025 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 3/18/2025 Approved ASHLEY THOMPSON
Green Building Rough 3/18/2025 Approved ASHLEY THOMPSON
HVAC-Rough 3/18/2025 Approved ASHLEY THOMPSON
Insulation 3/18/2025 Approved ASHLEY THOMPSON
Drywall Nailing 3/24/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Final 5/20/2025 Corrections Issued DANIEL VERA
Final 5/20/2025 Corrections Issued DANIEL VERA
Green Building Final 5/20/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 5/20/2025 Corrections Issued DANIEL VERA
PLUMBING-Final 5/20/2025 Not Ready for Inspection DANIEL VERA
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Not Required DANIEL VERA
Service/Power Release 5/20/2025 Not Required DANIEL VERA
Smoke Detectors 5/20/2025 Approved DANIEL VERA
ELECTRICAL-Final 6/5/2025 Approved ARAM AVEDISIAN
Final 6/5/2025 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 6/5/2025 Approved ARAM AVEDISIAN
HVAC-Final 6/5/2025 Approved ARAM AVEDISIAN
PLUMBING-Final 6/5/2025 Approved ARAM AVEDISIAN