341 S VERMONT AVE 90020
Certificate Information: 341 S VERMONT AVE 90020
- Application / Permit
- 24016-10000-11279
- Plan Check / Job No.
- B24LA06150
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- NEW ATTACHED EXTERIOR STORAGE ADDITION AND TENANT IMPROVEMENT TO EXISTING RESTAURANT INCLUDING <NON-SPRINKLERED BUILDING>:- Modify service counter and interior partitions screen wall, - Modify restroom for ADA compliance - Modify seating layout, ceiling and kiosks - Replace & relocate kitchen equipments - New sliding door - Addition of walk-up window
- Permit Issued
- Issued on 6/20/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | YOUNG KIM |
| Assigned to Zoning Architect | 4/11/2024 | BENNY WONG |
| Corrections Issued | 4/15/2024 | YOUNG KIM |
| Quality Review Completed | 4/17/2024 | KEN GILL |
| Building Plans Picked Up | 5/2/2024 | APPLICANT |
| Disabled Access Plans Picked Up | 5/2/2024 | APPLICANT |
| Applicant returned to address corrections | 12/11/2024 | YOUNG KIM |
| Applicant returned to address corrections | 1/16/2025 | YOUNG KIM |
| Plan Check Approved | 6/20/2025 | YOUNG KIM |
| Issued | 6/20/2025 | APPLICANT |
| CofO in Progress | 12/31/2025 | DARRYL ARNOLD |
| Permit Finaled | 2/5/2026 | ERNESTO CORRAL |
| CofO Issued | 2/5/2026 | ERNESTO CORRAL |
| Permit Finaled | 2/5/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| ZA Case | Cleared | 5/15/2024 | DAVID URITA |
| ZA Case | Cleared | 5/15/2024 | DAVID URITA |
| ZI | Cleared | 5/15/2024 | DAVID URITA |
| Historic Resource Verification | Cleared | 5/17/2024 | ELIZABETH GALLARDO |
| Historic Resource Verification | Cleared | 5/17/2024 | ELIZABETH GALLARDO |
| Redevelopment Project Area | Cleared | 5/17/2024 | ELIZABETH GALLARDO |
| Redevelopment Project Area | Cleared | 5/17/2024 | ELIZABETH GALLARDO |
| Miscellaneous | Cleared | 6/26/2024 | JOSE CARDENAS |
| Fire Marshal Fire Life Safety | Cleared | 8/21/2024 | WILLIAM JOHNS |
| Food Service Establishment | Cleared | 9/26/2024 | PAWAN VERMA |
| Green Code | Cleared | 10/24/2024 | AARON COSTA |
| DAS Clearance | Cleared | 11/7/2024 | YOUNG KIM |
| Zoning Plan Check | Cleared | 12/3/2024 | BENNY WONG |
| Food establishment approval | Cleared | 12/11/2024 | LACDHS APPROVED |
Contact Information
| Architect | Ong,, Francis Phat; Lic. No.: C18585 | 4122 GLENWOOD STREET IRVINE, CA 92604 |
| Contractor | C C K Builders Inc; Lic. No.: 855822-B | 625 W. KATELLA AVE UNIT 1 ORANGE, CA 92867 |
| Engineer | Phan,, Ben; Lic. No.: C57550 | 10822 WOODWARD LANE GARDEN GROVE, CA 92840 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/16/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Barrier | 9/16/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Subgrade | 9/16/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 9/17/2025 | Partial Approval | LUIS CCAMACHO |
| Footing/Foundation/Slab | 10/14/2025 | Partial Approval | TIMOTHY POWELL |
| Green Building Rough | 10/14/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| METHANE-Barrier | 10/14/2025 | Approved | TIMOTHY POWELL |
| METHANE-Rough | 10/14/2025 | Approved | TIMOTHY POWELL |
| METHANE-Subgrade | 10/14/2025 | Approved | TIMOTHY POWELL |
| Wood Frame | 10/14/2025 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 10/23/2025 | Partial Approval | TIMOTHY POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Partial Approval | TIMOTHY POWELL |
| Green Building Rough | 10/23/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 10/23/2025 | Partial Approval | TIMOTHY POWELL |
| Interior/Exterior Lathing | 10/27/2025 | Partial Approval | TIMOTHY POWELL |
| T-Bar Ceiling | 11/10/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 12/12/2025 | Approved | LUIS CCAMACHO |
| Final | 12/12/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Footing/Foundation/Slab | 12/12/2025 | Approved | LUIS CCAMACHO |
| Green Building Final | 12/12/2025 | Approved | LUIS CCAMACHO |
| Green Building Rough | 12/12/2025 | Approved | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 12/12/2025 | Approved | LUIS CCAMACHO |
| Special/Order Compliance | 12/12/2025 | Partial Inspection | REGINA MENDEZ |
| Wood Frame | 12/12/2025 | Approved | LUIS CCAMACHO |
| Final | 12/18/2025 | Corrections Issued | DARRYL ARNOLD |
| Final | 12/30/2025 | OK to Issue CofO | DARRYL ARNOLD |