4108 1/2 S BRONSON AVE 90008

Certificate Information: 4108 1/2 S BRONSON AVE 90008

Application / Permit
24016-10000-11101
Plan Check / Job No.
B24LA06050
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 2-CAR GARAGE TO 1-STORY ADU PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 10/10/2024
Issuing Office
Current Status
Issued on 10/10/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/3/2024 APPLICANT
Assigned to Plan Check Engineer 4/11/2024 KHEDER ALRAZAA
Corrections Issued 4/15/2024 KHEDER ALRAZAA
Quality Review Completed 4/19/2024 KEN GILL
Building Plans Picked Up 4/24/2024 APPLICANT
Applicant returned to address corrections 5/17/2024 KHEDER ALRAZAA
Plan Check Approved 8/1/2024 KHEDER ALRAZAA
Issued 10/10/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/4/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 5/4/2024 TREVOR QUAN
Sewer availability Cleared 5/4/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/6/2024 TREVOR QUAN
Construction within easement Cleared 6/12/2024 RIDWAN HARDY

Contact Information

Contractor Zorzoli Construction Inc; Lic. No.: 965210-B 1800 SAN PASQUAL ST      PASADENA, CA 91106
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/21/2025 Approved LUIS CASTRO
Sewer 2/5/2025 Partial Approval LUIS CASTRO
Footing/Foundation/Slab 5/19/2025 Partial Approval LUIS CASTRO
Reinforced Masonry Frame 6/6/2025 Partial Inspection LUIS CASTRO
PLUMBING-Rough 6/17/2025 Partial Approval LUIS CASTRO
Footing/Foundation/Slab 6/20/2025 No Access for Inspection SABAS ALONSO
Footing/Foundation/Slab 6/24/2025 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 7/2/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 9/8/2025 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 9/8/2025 Corrections Issued LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Partial Approval LUIS CASTRO
HVAC-Rough 9/8/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 9/8/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 10/29/2025 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 10/29/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Approved LUIS CASTRO
Insulation 10/29/2025 Partial Approval LUIS CASTRO
Interior/Exterior Lathing 11/7/2025 Partial Approval LUIS CASTRO
Insulation 12/1/2025 Partial Approval LUIS CASTRO
Drywall Nailing 12/12/2025 Partial Approval DEVON JACKSON
Green Building Rough 12/12/2025 Approved DEVON JACKSON
Insulation 12/12/2025 Approved DEVON JACKSON
Drywall Nailing 12/17/2025 Approved ALEX COLIN
Underground Mechanical 2/17/2026 Approved LUIS CASTRO