555 S GAYLEY AVE 90024
Certificate Information: 555 S GAYLEY AVE 90024
- Application / Permit
- 24016-10000-11018
- Plan Check / Job No.
- B24LA05990
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (11) Fraternity House
- Work Description
- EPLAN. Convert existing Library, Charter Room and Study Room into 3 bedrooms for a grand total of 19 bedrooms (The project currently has 16 bedroom.). Voluntary disable access improvements to existing private fraternity. Improvements consist of accessible parking, accessible path of travel, assessable ramp, remodel for one accessible unit including accessible bathroom, accessible kitchen casework, accessible restroom in the dining room, accessible restroom in the ground floor clubroom, Remove barriers for accessible laundry room, remove and install new lever locksets in common area doors.
- Permit Issued
- Issued on 4/22/2025
- Issuing Office
- Current Status
- Permit Finaled on 12/4/2025
Permit Application Status History
| Submitted | 4/5/2024 | APPLICANT |
| Assigned to Zoning Architect | 4/18/2024 | KAITA SAITO |
| Assigned to Plan Check Engineer | 4/18/2024 | KAVIAN REFAHI |
| Corrections Issued | 4/25/2024 | KAVIAN REFAHI |
| Quality Review Completed | 4/25/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 6/25/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 12/16/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 12/19/2024 | KAVIAN REFAHI |
| Plan Check Approved | 2/14/2025 | KAVIAN REFAHI |
| Issued | 4/22/2025 | APPLICANT |
| Permit Finaled | 12/3/2025 | DANIEL VARNUM |
Permit Application Clearance Information
| "Q" conditions | Cleared | 5/10/2024 | NATHAN ROMINE |
| ZI | Cleared | 5/15/2024 | JACKSON OLSON |
| Green Code | Cleared | 6/5/2024 | Fernando Flores |
| "Q" conditions | Cleared | 11/18/2024 | JACKSON OLSON |
| ZI | Cleared | 11/18/2024 | JACKSON OLSON |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2024 | DARIN LAM |
| Sewer availability | Cleared | 11/19/2024 | DARIN LAM |
| DAS Clearance | Cleared | 12/9/2024 | ELIZABETH TOMS |
| Zoning Plan Check | Cleared | 1/23/2025 | Fernando Flores |
Contact Information
| Architect | Villarruel,, Antonio; Lic. No.: NA25143 | , |
| Contractor | Do It Right Construction; Lic. No.: 857148-B | , |
| Contractor | L A Remodeling Inc; Lic. No.: 857148-B | , |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/30/2025 | Corrections Issued | RICARDO ROBLES |
| Footing/Foundation/Slab | 5/22/2025 | Approved | DANIEL VARNUM |
| Footing/Foundation/Slab | 5/29/2025 | Approved | DANIEL VARNUM |
| Wood Frame | 6/27/2025 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 7/3/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Drywall Nailing | 7/8/2025 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 7/8/2025 | Approved | PAUL DAVIDSON |
| Footing/Foundation/Slab | 7/16/2025 | Partial Approval | DANIEL VARNUM |
| Final | 11/14/2025 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Final | 11/14/2025 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 11/14/2025 | SGSOV No Gas | DANIEL VARNUM |
| Smoke Detectors | 11/14/2025 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 12/3/2025 | Permit Finaled | DANIEL VARNUM |
| Green Building Final | 12/3/2025 | Approved | DANIEL VARNUM |
| Smoke Detectors | 12/3/2025 | Approved | DANIEL VARNUM |