641 N WESTERN AVE UNIT A 90004
Certificate Information: 641 N WESTERN AVE UNIT A 90004
- Application / Permit
- 24016-10000-10933
- Plan Check / Job No.
- B24LA05930
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Change of use to Restauran and Interior Tenant Improvement wich includes a bar component as well as an omakase-style open-kitchen restaurant.
- Permit Issued
- Issued on 10/15/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | SALVADOR QUINTANILLA |
| Assigned to Zoning Architect | 4/4/2024 | CALEB WONG |
| Corrections Issued | 4/6/2024 | SALVADOR QUINTANILLA |
| Quality Review Completed | 4/9/2024 | PETER KIM |
| Building Plans Picked Up | 4/11/2024 | APPLICANT |
| Disabled Access Plans Picked Up | 5/2/2024 | APPLICANT |
| Applicant returned to address corrections | 6/17/2024 | SALVADOR QUINTANILLA |
| Plan Check Approved | 8/13/2024 | SALVADOR QUINTANILLA |
| Issued | 10/15/2024 | APPLICANT |
| CofO in Progress | 7/15/2025 | TIMOTHY POWELL |
| CofO in Progress | 8/18/2025 | ERNESTO CORRAL |
| Permit Finaled | 9/10/2025 | ERNESTO CORRAL |
| CofO Issued | 9/10/2025 | ERNESTO CORRAL |
| Permit Finaled | 9/10/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 4/18/2024 | AMBER CAMPBELL |
| Food establishment approval | Cleared | 6/17/2024 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 7/11/2024 | PAWAN VERMA |
| Green Code | Cleared | 7/31/2024 | SALVADOR QUINTANILLA |
| ZA Case | Cleared | 8/8/2024 | MATTHEW COMPANA |
| ZA Case | Cleared | 8/8/2024 | MATTHEW COMPANA |
| ZA Case | Cleared | 8/8/2024 | MATTHEW COMPANA |
| DAS Clearance | Cleared | 8/9/2024 | SALVADOR QUINTANILLA |
| Historic Resource Verification | Cleared | 8/9/2024 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 8/9/2024 | YASMINE BASHIRI |
| Zoning Plan Check | Cleared | 8/12/2024 | SALVADOR QUINTANILLA |
Contact Information
| Contractor | Bkb Enterprises Inc; Lic. No.: 1091258-B | 5256 S. MISSION ROAD SUITE 703-625 BONSALL, CA 92003 |
| Engineer | Harris,, James Edward; Lic. No.: C91562 | 5631 EDITA AVE WESTMINSTER, CA 92683 |
| Engineer | Kempton,, Justin John; Lic. No.: GE2385 | 5736 CORPORATE AVE CYPRESS, CA 90630 |
| Engineer | Tan,, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/28/2024 | Partial Inspection | TIMOTHY POWELL |
| Special/Order Compliance | 10/28/2024 | Partial Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 10/29/2024 | Partial Approval | RONALD JIMENEZ |
| Special/Order Compliance | 10/29/2024 | Corrections Issued | RONALD JIMENEZ |
| Footing/Foundation/Slab | 10/31/2024 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 11/5/2024 | Partial Approval | LUIS CCAMACHO |
| Footing/Foundation/Slab | 11/12/2024 | Partial Approval | PAUL BAZERKANIAN |
| Excavation/Setback/Form/Re-Bar | 11/26/2024 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 12/2/2024 | Partial Inspection | TIMOTHY POWELL |
| Wood Frame | 12/12/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 1/13/2025 | Partial Inspection | TIMOTHY POWELL |
| Wood Frame | 1/15/2025 | Partial Inspection | TIMOTHY POWELL |
| Insulation | 1/23/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 1/31/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Insulation | 1/31/2025 | Approved | TIMOTHY POWELL |
| Drywall Nailing | 2/4/2025 | Partial Inspection | TIMOTHY POWELL |
| Insulation | 2/4/2025 | Approved | TIMOTHY POWELL |
| Drywall Nailing | 2/6/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Drywall Nailing | 2/13/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 2/19/2025 | Partial Inspection | TIMOTHY POWELL |
| Drywall Nailing | 2/21/2025 | Partial Approval | TIMOTHY POWELL |
| Wood Frame | 4/11/2025 | Partial Approval | TIMOTHY POWELL |
| Final | 4/22/2025 | Partial Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Not Ready | TIMOTHY POWELL |
| Smoke Detectors | 4/22/2025 | Approved | TIMOTHY POWELL |
| Final | 4/29/2025 | Partial Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Not Ready | TIMOTHY POWELL |
| Final | 5/14/2025 | Partial Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 5/14/2025 | SGSOV Not Ready | TIMOTHY POWELL |
| Interior/Exterior Lathing | 5/19/2025 | Partial Approval | TIMOTHY POWELL |
| Final | 6/27/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Pre-Inspection | 6/27/2025 | Partial Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Not Ready | JEROME BLACKWOOD |
| Final | 7/1/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Approved | JEROME BLACKWOOD |
| Final | 7/14/2025 | OK to Issue CofO | TIMOTHY POWELL |