2821 1/2 S 8TH AVE 90018
Certificate Information: 2821 1/2 S 8TH AVE 90018
- Application / Permit
- 24016-10000-10894
- Plan Check / Job No.
- B24LA05908
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETAHCED (E) STORAGE ROOM AND TWO-CAR GARAGE TO DETACHED ONE STORY ADU PER STATE LAW. EXISTING NFPA 13D FIRE SPRINKLERS THRU OUT.
- Permit Issued
- Issued on 11/5/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2024 | MINA HABILI |
| Corrections Issued | 4/6/2024 | MINA HABILI |
| Building Plans Picked Up | 4/10/2024 | APPLICANT |
| Plan Check Approved | 11/1/2024 | DANIEL SMILEY |
| Issued | 11/5/2024 | APPLICANT |
| CofO in Progress | 1/23/2025 | JUSTIN HAWLEY |
| Permit Finaled | 1/28/2025 | DEROLD HAUFF |
| CofO Issued | 1/28/2025 | DEROLD HAUFF |
| Permit Finaled | 1/28/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/18/2024 | ISMAEL HERNANDEZ |
| ZA Case | Cleared | 4/18/2024 | JASON CHAN |
| Construction near power lines | Cleared | 8/15/2024 | RIDWAN HARDY |
| Address approval | Cleared | 10/22/2024 | CELINA MORENO |
| Sewer availability | Cleared | 10/22/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2024 | CELINA MORENO |
Contact Information
| Contractor | Line Electric Inc; Lic. No.: 910172-B | 4610 FLORAL DR LOS ANGELES, CA 90022 |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/26/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 11/26/2024 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 12/6/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 12/6/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 12/6/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 12/6/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 12/6/2024 | Approved | JUSTIN HAWLEY |
| Shower Pan | 12/6/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 12/6/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Drywall Nailing | 12/10/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Gas Test | 12/10/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 12/10/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 12/10/2024 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 12/13/2024 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 12/19/2024 | Partial Approval | JUSTIN HAWLEY |
| ELECTRICAL-Final | 1/17/2025 | Approved | JUSTIN HAWLEY |
| Final | 1/17/2025 | Corrections Issued | JUSTIN HAWLEY |
| HVAC-Final | 1/17/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Final | 1/17/2025 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Approved | JUSTIN HAWLEY |
| Service/Power Release | 1/17/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Smoke Detectors | 1/17/2025 | Approved | JUSTIN HAWLEY |
| Final | 1/22/2025 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 1/22/2025 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 1/22/2025 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 1/22/2025 | Approved | JUSTIN HAWLEY |