128 1/8 N LAKE ST 90026
Certificate Information: 128 1/8 N LAKE ST 90026
- Application / Permit
- 24016-10000-10855
- Plan Check / Job No.
- B24LA05888
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ***ePlan*** Convert (e) 3-car garage below (e) SFD at front of the lot to an ADU per LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 7/3/2024
- Issuing Office
- Current Status
- CofO Issued on 4/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2024 | SAMUEL GONZALEZ |
| Corrections Issued | 4/6/2024 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 5/7/2024 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 5/10/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 5/27/2024 | REZA HAGHIGHAT |
| Issued | 7/3/2024 | APPLICANT |
| CofO in Progress | 4/4/2025 | FREDDIE RIVERA |
| Permit Finaled | 4/5/2025 | DEROLD HAUFF |
| CofO Issued | 4/5/2025 | DEROLD HAUFF |
| Permit Finaled | 4/5/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/10/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/10/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2024 | DAVID LOPEZ |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: C37588 | 1801 S FAIRFAX AVE LOS ANGELES, CA 90019 |
| Architect | Feld,, Dovid Yitzchak; Lic. No.: NA37588 | , |
| Architect | Mcvay,, Bruce Cameron; Lic. No.: C11870 | 6440 E. EL ROBLE STREET LONG BEACH, CA 90815 |
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/29/2024 | Partial Inspection | JOHN QUINTANILLA |
| Deputy Drilled-In Anchors | 11/4/2024 | Conditional Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 11/4/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 11/19/2024 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 11/19/2024 | Approved | FREDDIE RIVERA |
| Wood Frame | 11/19/2024 | Corrections Issued | FREDDIE RIVERA |
| Deputy Wood Construction | 11/20/2024 | Conditional Approval | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 11/27/2024 | Partial Approval | FREDDIE RIVERA |
| Insulation | 12/3/2024 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 12/9/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 12/9/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 12/12/2024 | Approved | FREDDIE RIVERA |
| Final | 12/30/2024 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 12/30/2024 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 12/30/2024 | SGSOV Not Ready | WILLIAM SIERRA |
| Smoke Detectors | 12/30/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Wood Frame | 12/30/2024 | Approved | WILLIAM SIERRA |
| Final | 3/11/2025 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 3/11/2025 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/11/2025 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 3/11/2025 | Partial Inspection | FREDDIE RIVERA |
| Final | 3/19/2025 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 3/19/2025 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 3/19/2025 | Approved | FREDDIE RIVERA |
| Final | 3/26/2025 | Corrections Issued | FREDDIE RIVERA |