864 N VERMONT AVE 90029

Certificate Information: 864 N VERMONT AVE 90029

Application / Permit
24016-10000-10635
Plan Check / Job No.
B24LA05739
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
Change of use from Private Club/Pool Hall and Medical Office to Restaurant and combining two spaces into one.
Permit Issued
Issued on 4/9/2025
Issuing Office
Metro
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2024 APPLICANT
Assigned to Plan Check Engineer 4/1/2024 SALVADOR QUINTANILLA
Corrections Issued 4/1/2024 SALVADOR QUINTANILLA
Applicant returned to address corrections 5/29/2024 SALVADOR QUINTANILLA
Applicant returned to address corrections 8/20/2024 SALVADOR QUINTANILLA
Applicant returned to address corrections 2/10/2025 SALVADOR QUINTANILLA
Applicant returned to address corrections 3/19/2025 SALVADOR QUINTANILLA
Plan Check Approved 4/9/2025 SALVADOR QUINTANILLA
Issued 4/9/2025 APPLICANT
Permit Finaled 10/7/2025 ERNESTO CORRAL
CofO Issued 10/7/2025 ERNESTO CORRAL
Permit Finaled 10/7/2025 ERNESTO CORRAL

Permit Application Clearance Information

Miscellaneous Cleared 8/8/2024 MATHEW QUAN
ZA Case Cleared 8/8/2024 MATHEW QUAN
ZA Case Cleared 8/8/2024 MATHEW QUAN
Food Service Establishment Cleared 8/21/2024 BOGDAN SERBANESCU
Sewer availability Cleared 2/26/2025 CHRISTINA BRACO
Comm Cor/Mini-Mall Cleared 3/11/2025 DANIEL CORONADO
Specific Plan Cleared 3/11/2025 DANIEL CORONADO
Address approval Cleared 3/20/2025 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 3/20/2025 CHRISTINA BRACO
Food establishment approval Cleared 4/9/2025 LACDHS APPROVED

Contact Information

Contractor R C Pacific Construction Inc; Lic. No.: 721485-B 7070 GALILEE RD      ROSEVILLE, CA 95678

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/10/2025 Partial Approval LUIS CCAMACHO
Footing/Foundation/Slab 6/10/2025 Partial Approval LUIS CCAMACHO
Wood Frame 6/23/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 7/7/2025 Approved EDWIN GREGORYONA
Final 9/2/2025 Partial Inspection TIMOTHY POWELL
Green Building Final 9/2/2025 Not Ready for Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 9/2/2025 SGSOV Not Ready TIMOTHY POWELL
Smoke Detectors 9/2/2025 Not Ready for Inspection TIMOTHY POWELL
Final 10/1/2025 Partial Approval LUIS CCAMACHO
Green Building Final 10/1/2025 Approved LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 10/1/2025 SGSOV Approved LUIS CCAMACHO
Smoke Detectors 10/1/2025 Approved LUIS CCAMACHO