919 S CITRUS AVE 90036

Certificate Information: 919 S CITRUS AVE 90036

Application / Permit
24016-10000-10500
Plan Check / Job No.
B24LA05635
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 8/14/2024
Issuing Office
Current Status
CofO Issued on 1/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2024 APPLICANT
Assigned to Plan Check Engineer 3/29/2024 MADISON ODELL
Corrections Issued 3/29/2024 MADISON ODELL
Applicant returned to address corrections 8/8/2024 LUISANGEL VALENZUELA
Plan Check Approved 8/14/2024 GURUNATH NESARAJAH
Issued 8/14/2024 APPLICANT
CofO in Progress 12/31/2024 NICHOLAS LOPEZ
CofO Issued 1/13/2025 DEROLD HAUFF
Permit Finaled 1/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/3/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 4/8/2024 JESSICA OPINION
Sewer availability Cleared 4/8/2024 JESSICA OPINION
CPC Cleared 4/9/2024 SPENCER WEJROWSKI
Construction near power lines Cleared 8/5/2024 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Soul Builders Inc; Lic. No.: 1103425-B       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/29/2024 Corrections Issued RONNIE MINDANAO
Underground Mechanical 8/30/2024 Partial Approval NICHOLAS LOPEZ
Footing/Foundation/Slab 9/3/2024 Partial Approval RONNIE MINDANAO
Footing/Foundation/Slab 9/9/2024 Partial Approval RONNIE MINDANAO
Underground Mechanical 9/9/2024 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 9/11/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Partial Approval RONNIE MINDANAO
BUILDING-Rough-Frame 10/8/2024 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 10/8/2024 Approved RONNIE MINDANAO
Green Building Rough 10/8/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 10/8/2024 Not Ready for Inspection RONNIE MINDANAO
METHANE-Rough 10/8/2024 Approved RONNIE MINDANAO
PLUMBING-Rough 10/8/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Approved ENRIQUE MIRELES
HVAC-Rough 10/10/2024 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 10/16/2024 Corrections Issued RONNIE MINDANAO
Interior/Exterior Lathing 10/18/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 10/22/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Approved RONNIE MINDANAO
Green Building Rough 10/22/2024 Not Ready for Inspection RONNIE MINDANAO
Insulation 10/22/2024 Partial Approval RONNIE MINDANAO
Insulation 10/25/2024 Approved RONNIE MINDANAO
Drywall Nailing 10/30/2024 Approved RONNIE MINDANAO
Shower Pan 11/7/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 11/12/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 12/24/2024 Approved JEFFREY MEAD
Final 12/24/2024 Corrections Issued JEFFREY MEAD
Green Building Final 12/24/2024 Approved JEFFREY MEAD
Green Building Rough 12/24/2024 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 12/24/2024 SGSOV Approved JEFFREY MEAD
Smoke Detectors 12/24/2024 Not Ready for Inspection JEFFREY MEAD
Final 12/31/2024 OK to Issue CofO NICHOLAS LOPEZ
Smoke Detectors 12/31/2024 Approved NICHOLAS LOPEZ