1824 S ROBERTSON BLVD 90035
Certificate Information: 1824 S ROBERTSON BLVD 90035
- Application / Permit
- 24016-10000-10436
- Plan Check / Job No.
- B24LA05602
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) School - private
- Work Description
- CHANGE OF USE OF TWO STORY OFFICE BUILDING TO ELEMENTARY/MIDDLE SCHOOL.
- Permit Issued
- Issued on 10/30/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | ARMEN JIVALAGIAN |
| Assigned to Zoning Architect | 3/28/2024 | ARMEN JIVALAGIAN |
| Corrections Issued | 4/2/2024 | ARMEN JIVALAGIAN |
| Quality Review Completed | 4/4/2024 | PETER KIM |
| Building Plans Picked Up | 4/8/2024 | APPLICANT |
| Disabled Access Plans Picked Up | 4/17/2024 | APPLICANT |
| Applicant returned to address corrections | 6/11/2024 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 9/17/2024 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 10/1/2024 | ARMEN JIVALAGIAN |
| Plan Check Approved | 10/15/2024 | ARMEN JIVALAGIAN |
| Issued | 10/30/2024 | APPLICANT |
| CofO in Progress | 6/4/2025 | FARHAD DADBIN |
| CofO Issued | 6/5/2025 | DAVID TSAU |
| Permit Finaled | 6/5/2025 | DAVID TSAU |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2024 | WALLIE JONG |
| CPC | Cleared | 5/23/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 5/23/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 5/23/2024 | DANIEL CORONADO |
| Sewer availability | Cleared | 6/20/2024 | WALLIE JONG |
| DAS Clearance | Cleared | 7/16/2024 | ARMEN JIVALAGIAN |
| Community Plan Implem. Overlay | Cleared | 8/20/2024 | ISAIAH ROSS |
| Fire Marshal Fire Life Safety | Cleared | 9/3/2024 | WILLIAM JOHNS |
| Zoning Plan Check | Cleared | 10/1/2024 | ARMEN JIVALAGIAN |
Contact Information
| Architect | Mashihi,, Jacques; Lic. No.: C15922 | 10556 ASHTON AVENUE LOS ANGELES, CA 90024 |
| Contractor | Owner-Builder | , |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/11/2024 | Approved | FARHAD DADBIN |
| METHANE-Rough | 3/18/2025 | Approved | FARHAD DADBIN |
| Wood Frame | 3/18/2025 | Conditional Approval | FARHAD DADBIN |
| Wood Frame | 3/24/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Drywall Nailing | 4/2/2025 | Approved | FARHAD DADBIN |
| Final | 5/5/2025 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 5/5/2025 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 5/5/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 5/5/2025 | Approved | FARHAD DADBIN |
| Final | 5/14/2025 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 5/14/2025 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 5/14/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 5/23/2025 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 5/23/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 5/29/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Smoke Detectors | 5/29/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 6/4/2025 | OK to Issue CofO | FARHAD DADBIN |
| Smoke Detectors | 6/4/2025 | Approved | FARHAD DADBIN |