3668 S 2ND AVE 90018
Certificate Information: 3668 S 2ND AVE 90018
- Application / Permit
- 24016-10000-10427
- Plan Check / Job No.
- B24LA05596
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DET GARAGE W/ ATT STORAGE TO (N) 560 SF ADU PER GCS 65852.2 ALL WORK PER ENG.
- Permit Issued
- Issued on 9/16/2024
- Issuing Office
- Current Status
- CofO Issued on 3/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 3/29/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 4/8/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/13/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 8/27/2024 | LUISANGEL VALENZUELA |
| Issued | 9/16/2024 | APPLICANT |
| CofO in Progress | 3/5/2025 | JEFFREY MEAD |
| Permit Finaled | 3/9/2025 | DEROLD HAUFF |
| Permit Finaled | 3/9/2025 | DEROLD HAUFF |
| CofO Issued | 3/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/3/2024 | CHRISTINA BRACO |
| Miscellaneous | Cleared | 4/3/2024 | DANIEL CORONADO |
| Sewer availability | Cleared | 4/3/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2024 | CHRISTINA BRACO |
| HPOZ | Cleared | 4/30/2024 | DANIEL MATA |
| ZI | Cleared | 4/30/2024 | DANIEL MATA |
| Construction near power lines | Cleared | 8/6/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 16526 BLACKHAWK ST GRANADA HILLS, CA 91344 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/1/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Pre-Inspection | 10/1/2024 | Approved | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 10/3/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Pre-Inspection | 10/3/2024 | Approved | JUSTIN HAWLEY |
| Deputy Other (see comments) | 10/24/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 10/24/2024 | Partial Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 10/29/2024 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 10/29/2024 | Approved | JUSTIN HAWLEY |
| Deputy Wood Construction | 12/12/2024 | Conditional Approval | ALEX COLIN |
| BUILDING-Rough-Frame | 12/16/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 12/16/2024 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 12/16/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Rough | 12/16/2024 | Corrections Issued | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 12/16/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Rough | 12/16/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 12/16/2024 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 12/19/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 12/19/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 12/19/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 12/19/2024 | Partial Approval | JUSTIN HAWLEY |
| Shower Pan | 12/19/2024 | Approved | JUSTIN HAWLEY |
| Wood Frame | 12/19/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 12/27/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 12/27/2024 | Partial Approval | ALEX COLIN |
| Drywall Nailing | 1/6/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 1/6/2025 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 2/26/2025 | Approved | ENRIQUE MIRELES |
| Final | 2/26/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 2/26/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 2/26/2025 | Approved | ENRIQUE MIRELES |
| METHANE-Final | 2/26/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 2/26/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 2/26/2025 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 2/26/2025 | Approved | ENRIQUE MIRELES |
| Final | 3/5/2025 | OK to Issue CofO | JEFFREY MEAD |