154 S MOUNTAIN VIEW AVE 1-9 90057

Certificate Information: 154 S MOUNTAIN VIEW AVE 1-9 90057

Application / Permit
24016-10000-10389
Plan Check / Job No.
B24LA05559
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-plan. Convert existing storage and laundry room to ADU in an existing apartment
Permit Issued
Issued on 1/8/2025
Issuing Office
Current Status
CofO Issued on 3/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2024 APPLICANT
Assigned to Zoning Architect 4/18/2024 ELAHE MERRIKHI
Assigned to Plan Check Engineer 4/18/2024 ARSALAN SHABESTARI
Corrections Issued 5/6/2024 ARSALAN SHABESTARI
Quality Review Completed 5/22/2024 YOUNG KIM
Plan Check Approved 1/7/2025 ARSALAN SHABESTARI
Issued 1/8/2025 APPLICANT
CofO in Progress 11/10/2025 PAUL BAZERKANIAN
CofO in Progress 1/14/2026 ERNESTO CORRAL
Permit Finaled 3/2/2026 ERNESTO CORRAL
CofO Issued 3/2/2026 ERNESTO CORRAL
Permit Finaled 3/2/2026 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 6/21/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 6/21/2024 CHRISTINA BRACO
Sewer availability Cleared 6/21/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 6/26/2024 CHRISTINA BRACO
DAS Clearance Cleared 7/19/2024 Cristina Salazar
Fire Marshal Fire Life Safety Cleared 10/18/2024 PEJMAN NOORI
Green Code Cleared 11/6/2024 Cristina Salazar
Zoning Plan Check Cleared 11/27/2024 ELAHE MERRIKHI
Grading Pre-Inspection Cleared 12/20/2024 ARSALAN SHABESTARI

Contact Information

Contractor Funes Construction Inc; Lic. No.: 1028108-B       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 2/11/2025 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Rough 2/11/2025 Approved JEROME BLACKWOOD
Wood Frame 2/11/2025 Corrections Issued JEROME BLACKWOOD
Green Building Rough 4/7/2025 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 4/7/2025 Not Ready for Inspection JEROME BLACKWOOD
Green Building Rough 4/16/2025 Partial Approval JEROME BLACKWOOD
Wood Frame 4/16/2025 Partial Approval JEROME BLACKWOOD
Green Building Rough 4/23/2025 Approved JEROME BLACKWOOD
Wood Frame 4/23/2025 Approved JEROME BLACKWOOD
Drywall Nailing 4/25/2025 Approved JEROME BLACKWOOD
Interior/Exterior Lathing 5/2/2025 Partial Approval PAUL BAZERKANIAN
Final 6/6/2025 Corrections Issued JEROME BLACKWOOD
Green Building Final 6/6/2025 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 6/6/2025 SGSOV Not Ready JEROME BLACKWOOD
Smoke Detectors 6/6/2025 Not Ready for Inspection JEROME BLACKWOOD
Final 10/24/2025 Not Ready for Inspection PAUL BAZERKANIAN
Green Building Final 10/24/2025 Approved PAUL BAZERKANIAN
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Approved PAUL BAZERKANIAN
Smoke Detectors 10/24/2025 Approved PAUL BAZERKANIAN
Final 11/10/2025 OK to Issue CofO PAUL BAZERKANIAN