4119-4121 S HARVARD BLVD 90062

Certificate Information: 4119-4121 S HARVARD BLVD 90062

Application / Permit
24016-10000-10353
Plan Check / Job No.
B24LA05539
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
INTERIOR REMODEL OF (E) DUPLEX 2 bed 1 bath to 3 bed 2 bath
Permit Issued
Issued on 3/27/2024
Issuing Office
Metro
Current Status
Permit Finaled on 9/13/2024

Permit Application Status History

Submitted 3/27/2024 APPLICANT
Assigned to Plan Check Engineer 3/27/2024 NEHEMIAS RAMOS
Plan Check Approved 3/27/2024 NEHEMIAS RAMOS
Issued 3/27/2024 APPLICANT
Permit Finaled 9/12/2024 SABAS ALONSO

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/4/2024 Corrections Issued SABAS ALONSO
HVAC-Rough 6/4/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 6/4/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 6/7/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 6/11/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 6/11/2024 Partial Approval ANTHONY EGSON
PLUMBING-Rough 6/11/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 6/14/2024 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 6/14/2024 Approved SABAS ALONSO
PLUMBING-Rough 6/14/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 6/18/2024 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 6/24/2024 Approved SABAS ALONSO
Insulation 6/24/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 6/24/2024 Partial Approval SABAS ALONSO
PLUMBING-Rough 6/24/2024 Approved SABAS ALONSO
Drywall Nailing 6/27/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 7/5/2024 Approved SABAS ALONSO
Final 8/30/2024 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 8/30/2024 Approved SABAS ALONSO
Final 9/5/2024 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/5/2024 SGSOV Not Ready SABAS ALONSO
Final 9/10/2024 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/10/2024 SGSOV Approved SABAS ALONSO
Final 9/12/2024 Permit Finaled SABAS ALONSO
Green Building Final 9/12/2024 Approved SABAS ALONSO