300 S FALCON ST 90744

Certificate Information: 300 S FALCON ST 90744

Application / Permit
24016-10000-10316
Plan Check / Job No.
B24LA05509
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Manufacturing
Work Description
Eplan. Structural alteration to existing refinery for removal of existing tanks and pumps on second floor to replace with new tanks and pumps on new concrete forms
Permit Issued
Issued on 11/13/2024
Issuing Office
Current Status
Issued on 11/13/2024

Permit Application Status History

Submitted 3/28/2024 APPLICANT
Assigned to Plan Check Engineer 4/4/2024 SINA KHOSRAVI
Assigned to Zoning Architect 4/4/2024 BENNY WONG
Corrections Issued 4/10/2024 SINA KHOSRAVI
Quality Review Completed 4/26/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 5/16/2024 SINA KHOSRAVI
Applicant returned to address corrections 6/10/2024 SINA KHOSRAVI
Applicant returned to address corrections 6/25/2024 SINA KHOSRAVI
Applicant returned to address corrections 7/2/2024 SINA KHOSRAVI
Applicant returned to address corrections 7/17/2024 SINA KHOSRAVI
Plan Check Approved 8/23/2024 SINA KHOSRAVI
Issued 11/13/2024 APPLICANT

Permit Application Clearance Information

Port of LA Approval Cleared 4/19/2024 MELISSA HARNE
DAS Clearance Cleared 4/24/2024 Adam Hegazi
"Q" conditions Cleared 4/25/2024 DALIA MOKAYED
Green Code Cleared 5/9/2024 AARON COSTA
Zoning Plan Check Cleared 5/14/2024 Adam Hegazi

Contact Information

Contractor Marin Concrete Construction Inc; Lic. No.: 880073-A 541 PLACENTIA AVENUE      PERRIS, CA 92571
Engineer Igdelioglu,, Mustafa Bulent; Lic. No.: C92542 18825 46TH AVENUE NORTH      PLYMOUTH, MN 55446

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/22/2025 Corrections Issued MICHAEL PETRUSKO
Deputy Drilled-In Anchors 3/12/2025 Conditional Approval MICHAEL PETRUSKO
Excavation/Setback/Form/Re-Bar 3/12/2025 Approved MICHAEL PETRUSKO
Footing/Foundation/Slab 3/13/2025 Approved MICHAEL PETRUSKO
Deputy Drilled-In Anchors 4/3/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 11/6/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 11/6/2025 Conditional Approval MICHAEL PETRUSKO