728 S HIGHLAND AVE 90036
Certificate Information: 728 S HIGHLAND AVE 90036
- Application / Permit
- 24016-10000-10195
- Plan Check / Job No.
- B24LA05464
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert detached Garage to Accessory Dwelling Unit per CA GC 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 10/1/2024
- Issuing Office
- Current Status
- CofO Issued on 10/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2024 | KHUONG TRUONG |
| Corrections Issued | 4/2/2024 | KHUONG TRUONG |
| Applicant returned to address corrections | 8/24/2024 | GEORGE ALVAREZ |
| Plan Check Approved | 9/5/2024 | GEORGE ALVAREZ |
| Issued | 10/1/2024 | APPLICANT |
| CofO in Progress | 10/14/2025 | RONNIE MINDANAO |
| Permit Finaled | 10/19/2025 | DEROLD HAUFF |
| CofO Issued | 10/19/2025 | DEROLD HAUFF |
| Permit Finaled | 10/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 4/5/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2024 | CHRISTINA BRACO |
| ZA Case | Cleared | 5/20/2024 | NATHAN ROMINE |
| Construction near power lines | Cleared | 8/16/2024 | RIDWAN HARDY |
| Specific Plan | Cleared | 8/27/2024 | KHUONG TRUONG |
Contact Information
| Contractor | Home Front Build Inc; Lic. No.: 962293-B | 715 CYPRESS AVE LOS ANGELES, CA 90065 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/12/2024 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 12/16/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 1/13/2025 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 1/13/2025 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 1/21/2025 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 1/23/2025 | Approved | RONNIE MINDANAO |
| Shower Pan | 1/24/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 1/27/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 1/27/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 1/27/2025 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Rough | 1/27/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 1/29/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 1/29/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 2/4/2025 | Approved | RONNIE MINDANAO |
| Insulation | 2/13/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 2/25/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 8/8/2025 | Partial Inspection | RONNIE MINDANAO |
| Pre-Inspection | 8/8/2025 | Partial Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 8/25/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 8/25/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 8/25/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 8/25/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 8/25/2025 | Approved | RONNIE MINDANAO |
| HVAC-Final | 8/25/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 8/25/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 8/25/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 9/16/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 9/16/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 9/16/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 9/16/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 9/16/2025 | SGSOV Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 9/23/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 9/23/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 9/30/2025 | Conditional Approval | RONNIE MINDANAO |
| Final | 10/10/2025 | OK to Issue CofO | RONNIE MINDANAO |