448 N CROFT AVE 90048
Certificate Information: 448 N CROFT AVE 90048
- Application / Permit
- 24016-10000-10192
- Plan Check / Job No.
- B24LA05461
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: (1) EXISTING DETACHED GARAGE CONVERSION INTO A.D.U Per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/22/2024
- Issuing Office
- Current Status
- CofO Issued on 5/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | GEORGE JOLAKIAN |
| Corrections Issued | 4/24/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 4/30/2024 | RODOLFO ARIAS |
| Plan Check Approved | 8/22/2024 | GEORGE JOLAKIAN |
| Issued | 8/22/2024 | APPLICANT |
| CofO in Progress | 5/18/2025 | JEFFREY MEAD |
| Permit Finaled | 5/25/2025 | DEROLD HAUFF |
| CofO Issued | 5/25/2025 | DEROLD HAUFF |
| Permit Finaled | 5/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/30/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 4/30/2024 | CELINA MORENO |
| Sewer availability | Cleared | 4/30/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2024 | CELINA MORENO |
| Construction near power lines | Cleared | 5/17/2024 | TINA MIRANDA |
| Construction within easement | Cleared | 5/17/2024 | TINA MIRANDA |
| SB8 RUD | Cleared | 7/22/2024 | KEVIN SCHULTZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: NA35693 | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/26/2024 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 8/28/2024 | Approved | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Approved | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 8/29/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 9/12/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 9/12/2024 | Not Ready for Inspection | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Approved | JOSE MACIAS |
| Pre-Inspection | 10/11/2024 | Corrections Issued | JOSE MACIAS |
| Special/Order Compliance | 10/16/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 11/18/2024 | Corrections Issued | JOSE MACIAS |
| Insulation | 11/26/2024 | Corrections Issued | JOSE MACIAS |
| Insulation | 12/4/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 12/4/2024 | Corrections Issued | JOSE MACIAS |
| Drywall Nailing | 12/6/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 12/6/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 12/17/2024 | Approved | JOSE MACIAS |
| Final | 5/14/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 5/14/2025 | Approved | BRENDAN MORELLI |
| METHANE-Final | 5/14/2025 | Approved | BRENDAN MORELLI |
| METHANE-Rough | 5/14/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 5/14/2025 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 5/14/2025 | Approved | BRENDAN MORELLI |
| Wood Frame | 5/14/2025 | Approved | BRENDAN MORELLI |
| Final | 5/16/2025 | OK to Issue CofO | JEFFREY MEAD |