1309 S 2ND AVE 90019
Certificate Information: 1309 S 2ND AVE 90019
- Application / Permit
- 24016-10000-10143
- Plan Check / Job No.
- B24LA05417
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- AFFORDABLE HOUSING PUBLICLY FUNDED PROJECT OF AN (E) 2 STORIES 20 UNITS MULTI-FAMILY BUILDING WITH EXTERIOR AND INTERIOR RENOVATIONS. UPGRADE OF 3 (N) MOBILITY UNITS AND 1 (N) AUDIO-VISUAL UNITS. RENOVATIONS OF COMMON AREAS AND ACCESSIBLE PATH OF TRAVEL THROUGHOUT. NO STRUCTURAL WORK. NO ADDITIONAL SQ. FT.
- Permit Issued
- Issued on 10/1/2024
- Issuing Office
- Current Status
- Permit Finaled on 9/22/2025
Permit Application Status History
| Submitted | 3/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | VU NGUYEN |
| Corrections Issued | 4/2/2024 | VU NGUYEN |
| Quality Review Completed | 4/2/2024 | EUGENE BARBEAU |
| Applicant returned to address corrections | 5/16/2024 | VU NGUYEN |
| Applicant returned to address corrections | 6/5/2024 | VU NGUYEN |
| Plan Check Approved | 7/23/2024 | VU NGUYEN |
| Issued | 10/1/2024 | APPLICANT |
| Permit Finaled | 8/25/2025 | MARTIN TAVITIAN |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 4/10/2024 | RAFAEL FONTES |
| DAS Clearance | Cleared | 5/20/2024 | Eugene Barbeau |
| Green Code | Cleared | 5/28/2024 | AARON COSTA |
| Community Plan Implem. Overlay | Cleared | 6/11/2024 | ISAIAH ROSS |
| Redevelopment Project Area | Cleared | 6/12/2024 | YASMINE BASHIRI |
| Public Housing | Cleared | 6/17/2024 | SUNYOUNG KIM |
| Tenant Habitability Plan | Cleared | 7/15/2024 | RICARDO BOHORQUEZ |
Contact Information
| Architect | , ; Lic. No.: C38390 | , |
| Contractor | Ibca Llc; Lic. No.: 1112873-B | , |
| Contractor | Icon Builders; Lic. No.: 1112873-B | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 12/11/2024 | Conditional Approval | MARTIN TAVITIAN |
| Drywall Nailing | 12/13/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Insulation | 12/13/2024 | Approved | MARTIN TAVITIAN |
| Final | 8/20/2025 | Partial Inspection | MARTIN TAVITIAN |
| Green Building Final | 8/20/2025 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 8/20/2025 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 8/20/2025 | Approved | MARTIN TAVITIAN |
| Final | 8/25/2025 | Permit Finaled | MARTIN TAVITIAN |