919 S SHERBOURNE DR 90035
Certificate Information: 919 S SHERBOURNE DR 90035
- Application / Permit
- 24016-10000-10104
- Plan Check / Job No.
- B24LA05395
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install 2 Special Steel Cantilever Columns
- Permit Issued
- Issued on 10/10/2024
- Issuing Office
- Current Status
- CofC Issued on 3/6/2025
Permit Application Status History
| Submitted | 3/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | HANS SANTIAGO |
| Corrections Issued | 4/1/2024 | HANS SANTIAGO |
| Quality Review Completed | 4/10/2024 | CHARLES CHANG |
| Plan Check Approved | 4/18/2024 | ANDREW SANTIAGO |
| Issued | 10/10/2024 | APPLICANT |
| OK for CofC | 3/6/2025 | WINSTON DUNNING |
| CofC Issued | 3/6/2025 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 7/18/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/20/2024 | Conditional Approval | DARRYL ARNOLD |
| Pre-Inspection | 12/20/2024 | Corrections Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 12/23/2024 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 12/27/2024 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 12/27/2024 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/30/2024 | Partial Approval | LUIS CCAMACHO |
| Final | 2/6/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 2/6/2025 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 2/6/2025 | Corrections Issued | DARRYL ARNOLD |
| Final | 3/6/2025 | OK for CofC | WINSTON DUNNING |
| METHANE-Final | 3/6/2025 | Approved | WINSTON DUNNING |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Approved | WINSTON DUNNING |
| Smoke Detectors | 3/6/2025 | Approved | WINSTON DUNNING |