888 S FIGUEROA ST 90017
Certificate Information: 888 S FIGUEROA ST 90017
- Application / Permit
- 24016-10000-09890
- Plan Check / Job No.
- B24LA05270
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- EPLAN: PARTIAL FLOOR COMMON AREA IMPROVEMENTS TO THE FOLLOWING SPACES: MAIN LOBBY, ELEVATOR LOBBY, CAFE, MAIL ROOM, PARKING ELEVATOR LOBBY FOR LEVELS 1 & 2, PARKING GARAGE ENTRANCE, and PARKING GARAGE ROOF
- Permit Issued
- Issued on 9/17/2024
- Issuing Office
- Current Status
- Issued on 9/17/2024
Permit Application Status History
| Submitted | 3/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | QUAN NGHIEM |
| Assigned to Zoning Architect | 3/28/2024 | QUAN NGHIEM |
| Corrections Issued | 3/30/2024 | QUAN NGHIEM |
| Quality Review Completed | 4/2/2024 | PETER KIM |
| Applicant returned to address corrections | 5/8/2024 | QUAN NGHIEM |
| Applicant returned to address corrections | 5/22/2024 | QUAN NGHIEM |
| Applicant returned to address corrections | 5/24/2024 | QUAN NGHIEM |
| Plan Check Approved | 9/16/2024 | QUAN NGHIEM |
| Issued | 9/17/2024 | APPLICANT |
| Permit Finaled-Status Void | 7/15/2025 | PAUL BAZERKANIAN |
| Re-Activate Permit | 12/31/2025 | PAUL BAZERKANIAN |
Permit Application Clearance Information
| ZI | Cleared | 4/29/2024 | GEORGIA SMITH |
| Fire Marshal Fire Life Safety | Cleared | 5/22/2024 | DOMINIQUE MEDINA |
| Green Code | Cleared | 6/17/2024 | Jesse Arellano |
| DAS Clearance | Cleared | 7/29/2024 | ELIZABETH TOMS |
| Food establishment approval | Cleared | 8/26/2024 | LACDHS APPROVED |
| Zoning Plan Check | Cleared | 8/26/2024 | QUAN NGHIEM |
Contact Information
| Architect | Mangan,, Andrew T; Lic. No.: C26626 | 2314 28TH STREET #6 SANTA MONICA, CA 90405 |
| Contractor | Casco Contractors Llc; Lic. No.: 790706-B | , |
| Engineer | Volnyy,, Vladimir; Lic. No.: S4817 | 11342 PALA MESA DR NORTHRIDGE, CA 91326 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 6/18/2026 Time Frame: 12-2 |
Inspection Request History
| Pre-Inspection | 10/4/2024 | Not Ready for Inspection | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 10/8/2024 | Partial Approval | PAUL BAZERKANIAN |
| T-Bar Ceiling | 10/8/2024 | Partial Approval | PAUL BAZERKANIAN |
| T-Bar Ceiling | 10/18/2024 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 10/24/2024 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 11/20/2024 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 11/25/2024 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 12/9/2024 | Partial Approval | PAUL BAZERKANIAN |
| Final | 7/15/2025 | Partial Approval | PAUL BAZERKANIAN |
| Green Building Final | 7/15/2025 | Approved | PAUL BAZERKANIAN |
| Green Building Rough | 7/15/2025 | Approved | PAUL BAZERKANIAN |
| METHANE-Final | 7/15/2025 | Approved | PAUL BAZERKANIAN |
| METHANE-Rough | 7/15/2025 | Approved | PAUL BAZERKANIAN |
| Reinforced Concrete Frame | 7/15/2025 | Approved | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Approved | PAUL BAZERKANIAN |
| Smoke Detectors | 7/15/2025 | Approved | PAUL BAZERKANIAN |
| Pre-Inspection | 1/7/2026 | Partial Inspection | PAUL BAZERKANIAN |
| Pre-Inspection | 1/23/2026 | Partial Inspection | PAUL BAZERKANIAN |
| Pre-Inspection | 1/28/2026 | Partial Approval | PAUL BAZERKANIAN |
| Footing/Foundation/Slab | 2/13/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 2/24/2026 | Partial Approval | PAUL BAZERKANIAN |