- CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) - PER ENGINEER *Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2)
- Permit Issued
- Issued on 1/22/2025
- Issuing Office
- Current Status
- CofO Issued on 12/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 3/29/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 1/22/2025 | DANIEL ABRAMYAN |
| Issued | 1/22/2025 | APPLICANT |
| CofO in Progress | 12/9/2025 | LILIANA PORTILLO |
| Permit Finaled | 12/9/2025 | DEROLD HAUFF |
| CofO Issued | 12/9/2025 | DEROLD HAUFF |
| Permit Finaled | 12/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 4/25/2024 | NATHALY DE LA PAZ |
| Construction near power lines | Cleared | 8/4/2024 | RIDWAN HARDY |
| Address approval | Cleared | 9/27/2024 | DAVID VO |
| Sewer availability | Cleared | 9/27/2024 | DAVID VO |
| Grading Pre-Inspection | Cleared | 12/23/2024 | MICHAEL TEMPLE |
| CPC | Cleared | 12/24/2024 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2024 | DAVID VO |
Contact Information
| Contractor | L A Builder Construction Inc; Lic. No.: 933468-B | , |
| Engineer | Christiansen,, Scott; Lic. No.: NA37989 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/21/2025 | Conditional Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/27/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/27/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/27/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 3/27/2025 | Corrections Issued | LILIANA PORTILLO |
| Sewer | 3/27/2025 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 3/27/2025 | Partial Approval | LILIANA PORTILLO |
| Wood Frame | 3/27/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 5/2/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/6/2025 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/6/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 5/6/2025 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/6/2025 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/16/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 5/16/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 5/16/2025 | Approved | LILIANA PORTILLO |
| Insulation | 5/16/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2025 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 5/30/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 5/30/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 5/30/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 6/2/2025 | Approved | LILIANA PORTILLO |
| Shower Pan | 6/2/2025 | Approved | LILIANA PORTILLO |
| Final | 10/10/2025 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 10/10/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 10/10/2025 | Approved | LILIANA PORTILLO |
| Final | 10/24/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 11/17/2025 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 11/17/2025 | SGSOV No Gas | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/8/2025 | Approved | LILIANA PORTILLO |
| Final | 12/8/2025 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 12/8/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 12/8/2025 | Approved | LILIANA PORTILLO |