2133 E BAY ST 90021
Certificate Information: 2133 E BAY ST 90021
- Application / Permit
- 24016-10000-09644
- Plan Check / Job No.
- B24LA05134
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- PARTIAL CHANGE OF USE FROM WAREHOUSE TO OFFICE & TENANT IMPROVEMENT. NEW ADA ENTRY, NEW EXTERIOR STAIRS, RESTROOMS, NON-LOAD BEARING PARTITIONS. REPLACE EXISTING DOORS & WINDOWS. NEW EXIT AT REAR OF BLDG. NEW AWNINGS.
- Permit Issued
- Issued on 9/30/2024
- Issuing Office
- Current Status
- CofO Issued on 5/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2024 | APPLICANT |
| Assigned to Zoning Architect | 3/21/2024 | PRANITA SHAH |
| Assigned to Plan Check Engineer | 3/21/2024 | PRANITA SHAH |
| Disabled Access Plans Picked Up | 3/29/2024 | APPLICANT |
| Corrections Issued | 4/17/2024 | PRANITA SHAH |
| Quality Review Completed | 4/19/2024 | KEN GILL |
| Building Plans Picked Up | 5/1/2024 | APPLICANT |
| Applicant returned to address corrections | 5/16/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 9/20/2024 | PRANITA SHAH |
| Plan Check Approved | 9/26/2024 | PRANITA SHAH |
| Issued | 9/30/2024 | APPLICANT |
| CofO in Progress | 5/27/2025 | RONALD JIMENEZ |
| CofO Issued | 5/27/2025 | ERNESTO CORRAL |
| Permit Finaled | 5/27/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 5/30/2024 | DAVID LOPEZ |
| Redevelopment Project Area | Cleared | 6/5/2024 | YASMINE BASHIRI |
| DAS Clearance | Cleared | 6/13/2024 | SHINE LIN |
Contact Information
| Contractor | Curato Design/Build; Lic. No.: 1045316-B | 7748 SANTA MONICA BLVD WEST HOLLYWOOD, CA 90046 |
| Engineer | Hanna,, Emil Ramzy; Lic. No.: C63602 | 18925 GRANADA CIRCLE NORTHRIDGE, CA 91326 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 11/4/2024 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 11/4/2024 | Partial Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2024 | Partial Approval | RONALD JIMENEZ |
| Wood Frame | 11/22/2024 | Partial Approval | RONALD JIMENEZ |
| Footing/Foundation/Slab | 12/3/2024 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 12/3/2024 | Partial Approval | RONALD JIMENEZ |
| Insulation | 12/6/2024 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 12/13/2024 | Approved | RONALD JIMENEZ |
| Wood Frame | 1/27/2025 | Approved | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Approved | RONALD JIMENEZ |
| Interior/Exterior Lathing | 2/26/2025 | Approved | RONALD JIMENEZ |
| Final | 5/19/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Reinforced Masonry Frame | 5/19/2025 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 5/19/2025 | Approved | RONALD JIMENEZ |
| Final | 5/21/2025 | OK to Issue CofO | RONALD JIMENEZ |
| Special/Order Compliance | 5/21/2025 | Approved | RONALD JIMENEZ |