3746 S BUCKINGHAM ROAD 90016

Certificate Information: 3746 S BUCKINGHAM ROAD 90016

Application / Permit
24016-10000-09568
Plan Check / Job No.
B24LA05098
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 9/20/2024
Issuing Office
Current Status
CofO Issued on 5/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2024 APPLICANT
Assigned to Plan Check Engineer 3/28/2024 ALEC MOUSAKHANIAN
Corrections Issued 3/29/2024 ALEC MOUSAKHANIAN
Plan Check Approved 8/28/2024 ALEC MOUSAKHANIAN
Issued 9/20/2024 APPLICANT
CofO in Progress 5/16/2025 LUIS CASTRO
Permit Finaled 5/16/2025 DEROLD HAUFF
CofO Issued 5/16/2025 DEROLD HAUFF
Permit Finaled 5/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/4/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 5/4/2024 CELINA MORENO
Sewer availability Cleared 5/4/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/13/2024 CELINA MORENO
Construction near power lines Cleared 8/15/2024 RIDWAN HARDY

Contact Information

Contractor Bela Remodeling; Lic. No.: 1038287-B       ,
Engineer Hoerner,, John Brent; Lic. No.: S2145 24024 VIA CANDELA      VALENCIA, CA 91355

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2025 Partial Approval LUIS CASTRO
Deputy Drilled-In Anchors 2/3/2025 Partial Approval LUIS CASTRO
Footing/Foundation/Slab 2/3/2025 Partial Approval LUIS CASTRO
Footing/Foundation/Slab 2/11/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 3/10/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 3/10/2025 Approved LUIS CASTRO
Green Building Rough 3/10/2025 Partial Approval LUIS CASTRO
HVAC-Rough 3/10/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 3/10/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 3/13/2025 Approved ARTHUR NEGRETE
Green Building Rough 3/13/2025 Approved ARTHUR NEGRETE
HVAC-Rough 3/13/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 3/13/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 3/13/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/13/2025 Partial Inspection ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Approved LUIS CASTRO
Insulation 3/17/2025 Approved LUIS CASTRO
Drywall Nailing 3/25/2025 Approved ALEX COLIN
Interior/Exterior Lathing 3/25/2025 Approved ALEX COLIN
Shower Pan 3/25/2025 Approved ALEX COLIN
Sewer 4/7/2025 Approved LUIS CASTRO
ELECTRICAL-Final 5/15/2025 Approved LUIS CASTRO
Final 5/15/2025 OK to Issue CofO LUIS CASTRO
Green Building Final 5/15/2025 Approved LUIS CASTRO
HVAC-Final 5/15/2025 Approved LUIS CASTRO
PLUMBING-Final 5/15/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 5/15/2025 SGSOV Not Required LUIS CASTRO
Smoke Detectors 5/15/2025 Approved LUIS CASTRO