11463 W PEARL ST 90064
Certificate Information: 11463 W PEARL ST 90064
- Application / Permit
- 24016-10000-09167
- Plan Check / Job No.
- B24LA04961
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT EXISTING DETACHED GARAGE INTO A (N) 360 SF ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/3/2024
- Issuing Office
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 3/23/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/27/2024 | SERGIO MUNIZ |
| Plan Check Approved | 9/2/2024 | SERGIO MUNIZ |
| Issued | 9/3/2024 | APPLICANT |
| CofO in Progress | 5/5/2025 | KIRK SANDERS |
| Permit Finaled | 5/15/2025 | RICHARD STEINBACH |
| CofO Issued | 5/15/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/15/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2024 | DARIN LAM |
| Sewer availability | Cleared | 4/24/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2024 | DARIN LAM |
| Specific Plan | Cleared | 5/28/2024 | PEDRO AYALA |
| Construction near power lines | Cleared | 8/26/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/8/2024 | Conditional Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 10/10/2024 | Approved | KIRK SANDERS |
| Sewer | 10/10/2024 | Approved | KIRK SANDERS |
| Underground Mechanical | 10/10/2024 | Approved | KIRK SANDERS |
| Deputy Drilled-In Anchors | 10/11/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 10/11/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 10/30/2024 | Conditional Approval | KIRK SANDERS |
| Deputy Drilled-In Anchors | 11/7/2024 | Conditional Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 12/3/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 12/3/2024 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2024 | Conditional Approval | KIRK SANDERS |
| Deputy Drilled-In Anchors | 1/7/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 1/7/2025 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 1/8/2025 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 1/8/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 1/8/2025 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 1/8/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 1/8/2025 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 1/13/2025 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 1/13/2025 | Approved | KIRK SANDERS |
| Insulation | 1/13/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 1/13/2025 | Partial Approval | KIRK SANDERS |
| MERV13>=Rough | 1/13/2025 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 1/13/2025 | Approved | KIRK SANDERS |
| Wood Frame | 1/13/2025 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Approved | EVAN COOPER |
| Insulation | 1/27/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 1/31/2025 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/11/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 2/11/2025 | Partial Inspection | KIRK SANDERS |
| Shower Pan | 2/11/2025 | Partial Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 4/9/2025 | Corrections Issued | KIRK SANDERS |
| Final | 4/9/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 4/9/2025 | Corrections Issued | KIRK SANDERS |
| MERV13>=Final | 4/9/2025 | Approved | KIRK SANDERS |
| PLUMBING-Final | 4/9/2025 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/9/2025 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 4/9/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 4/25/2025 | Approved | KIRK SANDERS |
| Final | 4/25/2025 | Partial Approval | KIRK SANDERS |
| HVAC-Final | 4/25/2025 | Conditional Approval | KIRK SANDERS |
| PLUMBING-Final | 4/25/2025 | Approved | KIRK SANDERS |
| Final | 5/5/2025 | OK to Issue CofO | KIRK SANDERS |