1253 S BARRY AVE 1-19 90025

Certificate Information: 1253 S BARRY AVE 1-19 90025

Application / Permit
24016-10000-09143
Plan Check / Job No.
B24LA04926
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT AN EXISTING STORAGE ROOM ADJACENT TO LOBBY INTO ONE NEW ATTACHED A.D.U. Via the Multiple ADUs per State Law option under CA Govt. Code 65852.2(e)(1)(C). Exist. 3-Story Apartment Building to Remain; DO NOT ISSUE ANY PERMITS - $400.00 INVESTIGATION FEE DUE FOR THE FOLLOWING WORK DONE WITHOUT PERMITS: STARTED WITHOUT PERMIT OR INSPECTION ELEVATOR STATE #94651 INSPECTOR:MICHAEL COONEY PHONE:(310) 914-3970
Permit Issued
Issued on 11/5/2024
Issuing Office
Current Status
Issued on 11/5/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/28/2024 APPLICANT
Assigned to Plan Check Engineer 5/30/2024 SERGIO GUTIERREZ
Assigned to Zoning Architect 5/30/2024 KAREN MEZA-MORALES
Corrections Issued 6/4/2024 SERGIO GUTIERREZ
Quality Review Completed 6/5/2024 RODOLFO ARIAS
Applicant returned to address corrections 8/5/2024 SERGIO GUTIERREZ
Plan Check Approved 10/22/2024 SERGIO GUTIERREZ
Issued 11/5/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/1/2024 DARIN LAM
Sewer availability Cleared 7/1/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 7/2/2024 DARIN LAM
Specific Plan Cleared 7/30/2024 PEDRO AYALA
Fire Marshal Fire Life Safety Cleared 9/11/2024 DOMINIQUE MEDINA
Green Code Cleared 9/18/2024 AARON COSTA
DAS Clearance Cleared 9/19/2024 CAROLYNN NEPOMUCENO
Zoning Plan Check Cleared 9/27/2024 KAREN MEZA-MORALES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/22/2025 Conditional Approval CASIMIR BRITTON
Light Gage Steel Frame 7/8/2025 Conditional Approval CASIMIR BRITTON
Insulation 8/26/2025 Approved DANIEL VARNUM
Interior/Exterior Lathing 8/26/2025 Approved DANIEL VARNUM
Drywall Nailing 9/8/2025 Approved CASIMIR BRITTON
Final 10/29/2025 No Access for Inspection CASIMIR BRITTON
Green Building Final 10/29/2025 No Access for Inspection CASIMIR BRITTON
METHANE-Final 10/29/2025 No Access for Inspection CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Not Ready CASIMIR BRITTON
Smoke Detectors 10/29/2025 No Access for Inspection CASIMIR BRITTON
Final 7/2/2026 Not Ready for Inspection DERRICK SPENCER
Green Building Final 7/2/2026 Approved DERRICK SPENCER
METHANE-Final 7/2/2026 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 7/2/2026 SGSOV Approved DERRICK SPENCER
Smoke Detectors 7/2/2026 Approved DERRICK SPENCER