131 3/4 S GLESS ST 90033
Certificate Information: 131 3/4 S GLESS ST 90033
- Application / Permit
- 24016-10000-09068
- Plan Check / Job No.
- B24LA04886
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. CONVERT (E) PLAY ROOM INTO ADU PER CA Govt. Code 65852.2(e)(1)(A), CONVERT (E) PORTION PORCH INTO STORAGE, ADD EXTERIOR W/D MAIN HOUSE, PROPOSED NEW DRIVEWAY PER WFPP.
- Permit Issued
- Issued on 2/7/2025
- Issuing Office
- Current Status
- CofO Issued on 3/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2024 | AMY GUEVARRA |
| Corrections Issued | 3/27/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 5/24/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 5/28/2024 | ZAW HAN |
| Applicant returned to address corrections | 7/2/2024 | ZAW HAN |
| Applicant returned to address corrections | 10/19/2024 | ZAW HAN |
| Applicant returned to address corrections | 12/9/2024 | ZAW HAN |
| Applicant returned to address corrections | 12/25/2024 | ZAW HAN |
| Plan Check Approved | 2/7/2025 | ZAW HAN |
| Issued | 2/7/2025 | APPLICANT |
| CofO in Progress | 3/6/2026 | FREDDIE RIVERA |
| Permit Finaled | 3/7/2026 | DEROLD HAUFF |
| CofO Issued | 3/7/2026 | DEROLD HAUFF |
| Permit Finaled | 3/7/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2024 | JEANIE LAM |
| Permit | Cleared | 5/20/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/20/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2024 | JEANIE LAM |
| Sewer availability | Cleared | 5/23/2024 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/8/2025 | Partial Inspection | OSVALDO PARAMO |
| Sewer | 6/5/2025 | Partial Approval | JUSTIN HAWLEY |
| Underground Mechanical | 6/5/2025 | Partial Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 6/13/2025 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/26/2025 | Approved | ARTHUR NEGRETE |
| Pre-Inspection | 7/18/2025 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Partial Approval | LUIS CASTRO |
| Wood Frame | 8/14/2025 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2025 | Partial Approval | FREDDIE RIVERA |
| MERV13>=Rough | 8/18/2025 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 8/18/2025 | Partial Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/3/2025 | Partial Approval | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 9/3/2025 | Corrections Issued | FREDDIE RIVERA |
| Special/Order Compliance | 9/3/2025 | Partial Inspection | OSVALDO PARAMO |
| Underground Mechanical | 9/3/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/10/2025 | Partial Approval | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 9/10/2025 | Approved | FREDDIE RIVERA |
| Insulation | 9/12/2025 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 9/17/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 9/17/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 10/16/2025 | Partial Approval | REGINA MENDEZ |
| Excavation/Setback/Form/Re-Bar | 10/22/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/31/2025 | Conditional Approval | FREDDIE RIVERA |
| Final | 10/31/2025 | Corrections Issued | FREDDIE RIVERA |
| MERV13>=Final | 10/31/2025 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 10/31/2025 | Approved | FREDDIE RIVERA |
| METHANE-Final | 10/31/2025 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Rough | 10/31/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 10/31/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/7/2025 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 11/7/2025 | Approved | SCOTT FINNILA |
| Final | 11/7/2025 | Corrections Issued | SCOTT FINNILA |
| HVAC-Final | 11/7/2025 | Approved | SCOTT FINNILA |
| METHANE-Final | 11/7/2025 | Approved | SCOTT FINNILA |
| METHANE-Rough | 11/7/2025 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 11/7/2025 | Approved | SCOTT FINNILA |
| Service/Power Release | 2/19/2026 | Approved | FREDDIE RIVERA |
| Final | 3/6/2026 | OK to Issue CofO | FREDDIE RIVERA |