6291 W DEL VALLE DR 90048
Certificate Information: 6291 W DEL VALLE DR 90048
- Application / Permit
- 24016-10000-08861
- Plan Check / Job No.
- B24LA04758
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Convert existing garage (283.5 sf) and rec room (238 sf) to an ADU (521.5sqft) per state law ***COMPLY WITH DEPARTMENT ORDER***
- Permit Issued
- Issued on 10/4/2024
- Issuing Office
- Current Status
- CofO Issued on 1/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2024 | KHUONG TRUONG |
| Corrections Issued | 3/21/2024 | KHUONG TRUONG |
| Applicant returned to address corrections | 6/15/2024 | KHUONG TRUONG |
| Plan Check Approved | 7/26/2024 | JOSEPH RAFOLS |
| Issued | 10/4/2024 | APPLICANT |
| CofO in Progress | 12/12/2024 | PETER RUBIO |
| Permit Finaled | 1/15/2025 | DANIEL SANCHEZ |
| CofO Issued | 1/15/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 4/20/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2024 | TREVOR QUAN |
| City Hist. Cultural Monument | Cleared | 7/16/2024 | LAMBERT GIESSINGER |
| HPOZ | Cleared | 7/16/2024 | LAMBERT GIESSINGER |
| Hist. Property Cntrct Mgr Appr | Cleared | 7/16/2024 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 7/16/2024 | LAMBERT GIESSINGER |
| ZA Case | Cleared | 7/23/2024 | DALIA MOKAYED |
Contact Information
| Contractor | Radd Construction; Lic. No.: 922522-B | , |
| Engineer | Golabtounkar,, Tony Hamid; Lic. No.: C49104 | 1434 WESTWOOD BLVD ST 17 LOS ANGELES, CA 90024 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/11/2024 | Approved | PETER RUBIO |
| Footing/Foundation/Slab | 10/15/2024 | Approved | RUBEN PEREZ |
| ELECTRICAL-Rough | 10/30/2024 | Approved | PETER RUBIO |
| Insulation | 10/30/2024 | Approved | PETER RUBIO |
| PLUMBING-Rough | 10/30/2024 | Approved | PETER RUBIO |
| Wood Frame | 10/30/2024 | Approved | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Approved | PETER RUBIO |
| Structural Steel Frame | 10/31/2024 | Approved | PETER RUBIO |
| Drywall Nailing | 11/4/2024 | Approved | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Not Ready | RUBEN PEREZ |
| BUILDING-Rough-Frame | 12/2/2024 | Approved | PETER RUBIO |
| Final | 12/2/2024 | Corrections Issued | PETER RUBIO |
| Green Building Final | 12/2/2024 | Approved | PETER RUBIO |
| Green Building Rough | 12/2/2024 | Approved | PETER RUBIO |
| METHANE-Final | 12/2/2024 | Approved | PETER RUBIO |
| METHANE-Rough | 12/2/2024 | Approved | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 12/2/2024 | SGSOV Not Ready | PETER RUBIO |
| Smoke Detectors | 12/2/2024 | Approved | PETER RUBIO |
| Final | 12/11/2024 | OK to Issue CofO | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 12/11/2024 | SGSOV Approved | PETER RUBIO |