EPLAN. CONVERT PORTION OF EXISTING UNIT INTO A STORAGE ROOM IN EXISTING APARTMENT BUILDING
Permit Issued
Issued on 4/18/2024
Issuing Office
Current Status
CofO Issued on 3/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2024 APPLICANT
Assigned to Plan Check Engineer 3/18/2024 ADAM HEGAZI
Corrections Issued 3/19/2024 ADAM HEGAZI
Plan Check Approved 4/2/2024 AUNG SOE
Issued 4/18/2024 APPLICANT
CofO in Progress 3/11/2025 RAMAZANALI ALMASI
Permit Finaled 3/11/2025 ERNESTO CORRAL
CofO Issued 3/11/2025 ERNESTO CORRAL
Permit Finaled 3/11/2025 ERNESTO CORRAL

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Dovid, Yitzchak Feld; Lic. No.: NA37588       ,
Architect Mcvay,, Bruce Cameron; Lic. No.: C11870 6440 E. EL ROBLE STREET      LONG BEACH, CA 90815
Contractor Model Construction; Lic. No.: 1073367-B       ,
Contractor Model Maintenance Llc; Lic. No.: 1073367-B       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/28/2024 Not Ready for Inspection RAMAZANALI ALMASI
Pre-Inspection 6/14/2024 Partial Inspection RAMAZANALI ALMASI
METHANE-Rough 9/26/2024 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 9/26/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 12/20/2024 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Final 12/20/2024 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Rough 12/20/2024 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Not Ready RAMAZANALI ALMASI
Smoke Detectors 12/20/2024 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 12/20/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 1/24/2025 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Final 1/24/2025 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Rough 1/24/2025 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Not Ready RAMAZANALI ALMASI
Smoke Detectors 1/24/2025 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 1/24/2025 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 2/7/2025 Partial Approval RAMAZANALI ALMASI
Insulation 2/10/2025 Approved RAMAZANALI ALMASI
Drywall Nailing 3/5/2025 Approved RAMAZANALI ALMASI
Final 3/5/2025 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Final 3/5/2025 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Rough 3/5/2025 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV Not Ready RAMAZANALI ALMASI
Smoke Detectors 3/5/2025 Not Ready for Inspection RAMAZANALI ALMASI
Final 3/10/2025 Conditional Approval RAMAZANALI ALMASI
METHANE-Final 3/10/2025 Approved RAMAZANALI ALMASI
METHANE-Rough 3/10/2025 Approved RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 3/10/2025 SGSOV Approved RAMAZANALI ALMASI
Smoke Detectors 3/10/2025 Approved RAMAZANALI ALMASI
Wood Frame 3/10/2025 Approved RAMAZANALI ALMASI
Final 3/11/2025 OK to Issue CofO RAMAZANALI ALMASI