2251 W MERTON AVE 90041
Certificate Information: 2251 W MERTON AVE 90041
- Application / Permit
- 24016-10000-08645
- Plan Check / Job No.
- B24LA04625
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN. CONVERT PORTION OF EXISTING UNIT INTO A STORAGE ROOM IN EXISTING APARTMENT BUILDING
- Permit Issued
- Issued on 4/18/2024
- Issuing Office
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2024 | ADAM HEGAZI |
| Corrections Issued | 3/19/2024 | ADAM HEGAZI |
| Plan Check Approved | 4/2/2024 | AUNG SOE |
| Issued | 4/18/2024 | APPLICANT |
| CofO in Progress | 3/11/2025 | RAMAZANALI ALMASI |
| Permit Finaled | 3/11/2025 | ERNESTO CORRAL |
| CofO Issued | 3/11/2025 | ERNESTO CORRAL |
| Permit Finaled | 3/11/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Dovid, Yitzchak Feld; Lic. No.: NA37588 | , |
| Architect | Mcvay,, Bruce Cameron; Lic. No.: C11870 | 6440 E. EL ROBLE STREET LONG BEACH, CA 90815 |
| Contractor | Model Construction; Lic. No.: 1073367-B | , |
| Contractor | Model Maintenance Llc; Lic. No.: 1073367-B | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/28/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Pre-Inspection | 6/14/2024 | Partial Inspection | RAMAZANALI ALMASI |
| METHANE-Rough | 9/26/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 9/26/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 12/20/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Final | 12/20/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Rough | 12/20/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 12/20/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 12/20/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 1/24/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Final | 1/24/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Rough | 1/24/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 1/24/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 1/24/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 2/7/2025 | Partial Approval | RAMAZANALI ALMASI |
| Insulation | 2/10/2025 | Approved | RAMAZANALI ALMASI |
| Drywall Nailing | 3/5/2025 | Approved | RAMAZANALI ALMASI |
| Final | 3/5/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Final | 3/5/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Rough | 3/5/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 3/5/2025 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 3/5/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 3/10/2025 | Conditional Approval | RAMAZANALI ALMASI |
| METHANE-Final | 3/10/2025 | Approved | RAMAZANALI ALMASI |
| METHANE-Rough | 3/10/2025 | Approved | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 3/10/2025 | SGSOV Approved | RAMAZANALI ALMASI |
| Smoke Detectors | 3/10/2025 | Approved | RAMAZANALI ALMASI |
| Wood Frame | 3/10/2025 | Approved | RAMAZANALI ALMASI |
| Final | 3/11/2025 | OK to Issue CofO | RAMAZANALI ALMASI |