902 N DEXTER ST 90042
Certificate Information: 902 N DEXTER ST 90042
- Application / Permit
- 24016-10000-08616
- Plan Check / Job No.
- B24LA04605
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF EX. DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GSC 65852.2(e)(1)(A).
- Permit Issued
- Issued on 7/30/2024
- Issuing Office
- Current Status
- CofO Issued on 2/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2024 | ROSENDO MEDINA |
| Corrections Issued | 3/19/2024 | ROSENDO MEDINA |
| Plan Check Approved | 6/6/2024 | ROSENDO MEDINA |
| Issued | 7/30/2024 | APPLICANT |
| CofO in Progress | 2/19/2025 | THOMAS LOGRASSO |
| Permit Finaled | 2/23/2025 | DEROLD HAUFF |
| Permit Finaled | 2/23/2025 | DEROLD HAUFF |
| CofO Issued | 2/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 4/5/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2024 | AMBER CAMPBELL |
| Miscellaneous | Cleared | 4/15/2024 | ALBERT TAM |
| Hydrant and Access approval | Cleared | 4/26/2024 | MATTHEW CRAIG |
| Grading Pre-Inspection | Cleared | 6/3/2024 | MICHAEL TEMPLE |
Contact Information
| Contractor | Srk Construction Inc; Lic. No.: 1040488-B | , |
| Engineer | Zimmermann,, Scott Andrew; Lic. No.: CH5944 | 278 LIBERTY ST SAN FRANCISCO, CA 94114 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/26/2024 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/27/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Sewer | 8/30/2024 | Not Ready for Inspection | LUIS CASTRO |
| Underground Mechanical | 8/30/2024 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 9/3/2024 | Partial Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/10/2024 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 9/12/2024 | Corrections Issued | THOMAS LOGRASSO |
| Sewer | 9/26/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 10/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/15/2024 | Corrections Issued | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 10/15/2024 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/5/2024 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 11/5/2024 | Conditional Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 11/5/2024 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 11/5/2024 | Partial Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 11/7/2024 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/13/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 11/13/2024 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 11/13/2024 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 11/18/2024 | Conditional Approval | THOMAS LOGRASSO |
| Insulation | 11/18/2024 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 11/27/2024 | Approved | ANTHONY RAMOS |
| Final | 2/12/2025 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 2/12/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 2/12/2025 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Not Required | THOMAS LOGRASSO |
| Smoke Detectors | 2/12/2025 | Approved | THOMAS LOGRASSO |
| Final | 2/14/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 2/14/2025 | Approved | THOMAS LOGRASSO |
| Final | 2/19/2025 | OK to Issue CofO | THOMAS LOGRASSO |