902 N DEXTER ST 90042

Certificate Information: 902 N DEXTER ST 90042

Application / Permit
24016-10000-08616
Plan Check / Job No.
B24LA04605
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF EX. DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GSC 65852.2(e)(1)(A).
Permit Issued
Issued on 7/30/2024
Issuing Office
Current Status
CofO Issued on 2/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2024 APPLICANT
Assigned to Plan Check Engineer 3/18/2024 ROSENDO MEDINA
Corrections Issued 3/19/2024 ROSENDO MEDINA
Plan Check Approved 6/6/2024 ROSENDO MEDINA
Issued 7/30/2024 APPLICANT
CofO in Progress 2/19/2025 THOMAS LOGRASSO
Permit Finaled 2/23/2025 DEROLD HAUFF
Permit Finaled 2/23/2025 DEROLD HAUFF
CofO Issued 2/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/5/2024 AMBER CAMPBELL
Sewer availability Cleared 4/5/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 4/9/2024 AMBER CAMPBELL
Miscellaneous Cleared 4/15/2024 ALBERT TAM
Hydrant and Access approval Cleared 4/26/2024 MATTHEW CRAIG
Grading Pre-Inspection Cleared 6/3/2024 MICHAEL TEMPLE

Contact Information

Contractor Srk Construction Inc; Lic. No.: 1040488-B       ,
Engineer Zimmermann,, Scott Andrew; Lic. No.: CH5944 278 LIBERTY ST      SAN FRANCISCO, CA 94114

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/26/2024 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 8/27/2024 Not Ready for Inspection THOMAS LOGRASSO
Sewer 8/30/2024 Not Ready for Inspection LUIS CASTRO
Underground Mechanical 8/30/2024 Approved LUIS CASTRO
Footing/Foundation/Slab 9/3/2024 Partial Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 9/10/2024 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 9/12/2024 Corrections Issued THOMAS LOGRASSO
Sewer 9/26/2024 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 10/10/2024 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 10/10/2024 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 10/10/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 10/15/2024 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 10/15/2024 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 11/5/2024 Partial Approval THOMAS LOGRASSO
Insulation 11/5/2024 Conditional Approval THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 11/5/2024 Approved THOMAS LOGRASSO
Underground Mechanical 11/5/2024 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 11/7/2024 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 11/13/2024 Approved THOMAS LOGRASSO
Insulation 11/13/2024 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 11/13/2024 Partial Approval THOMAS LOGRASSO
Drywall Nailing 11/18/2024 Conditional Approval THOMAS LOGRASSO
Insulation 11/18/2024 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 11/27/2024 Approved ANTHONY RAMOS
Final 2/12/2025 Corrections Issued THOMAS LOGRASSO
Green Building Final 2/12/2025 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 2/12/2025 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Not Required THOMAS LOGRASSO
Smoke Detectors 2/12/2025 Approved THOMAS LOGRASSO
Final 2/14/2025 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 2/14/2025 Approved THOMAS LOGRASSO
Final 2/19/2025 OK to Issue CofO THOMAS LOGRASSO