1434 1/4 S STANLEY AVE 90019

Certificate Information: 1434 1/4 S STANLEY AVE 90019

Application / Permit
24016-10000-08614
Plan Check / Job No.
B24LA04602
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Detached 1-Story Garage and Portion of Laundry Room Conversion to ADU per lamc 12.22 A.33 (c) and (d). All Work Done per WFPP.
Permit Issued
Issued on 5/16/2024
Issuing Office
Current Status
CofO Issued on 11/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2024 APPLICANT
Assigned to Plan Check Engineer 3/20/2024 DAVID CASTILLO
Corrections Issued 3/20/2024 DAVID CASTILLO
Applicant returned to address corrections 4/23/2024 DAVID CASTILLO
Applicant returned to address corrections 4/24/2024 DAVID CASTILLO
Applicant returned to address corrections 4/26/2024 DAVID CASTILLO
Plan Check Approved 5/6/2024 REZA HAGHIGHAT
Plan Check Approved 5/7/2024 REZA HAGHIGHAT
Issued 5/16/2024 APPLICANT
CofO in Progress 8/16/2024 ARTHUR NEGRETE
Permit Finaled 11/21/2024 DEROLD HAUFF
Permit Finaled 11/21/2024 DEROLD HAUFF
CofO Issued 11/21/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/28/2024 WALLIE JONG
Sewer availability Cleared 3/28/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/1/2024 WALLIE JONG

Contact Information

Contractor E H D Builders Inc; Lic. No.: 1034101-B 18375 VENTURA BLVD STE #122      TARZANA, CA 91356

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/20/2024 Partial Inspection ARTHUR NEGRETE
Footing/Foundation/Slab 5/28/2024 Not Ready for Inspection ARTHUR NEGRETE
METHANE-Barrier 5/28/2024 Not Ready for Inspection ARTHUR NEGRETE
METHANE-Subgrade 5/28/2024 Not Ready for Inspection ARTHUR NEGRETE
Underground Mechanical 5/28/2024 Not Ready for Inspection ARTHUR NEGRETE
Deputy Drilled-In Anchors 5/30/2024 Conditional Approval RICHARD DOCKUS
Special/Order Compliance 5/30/2024 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 5/30/2024 Partial Approval ARTHUR NEGRETE
Footing/Foundation/Slab 6/3/2024 Approved ENRIQUE MIRELES
METHANE-Barrier 6/3/2024 Approved ENRIQUE MIRELES
METHANE-Subgrade 6/3/2024 Approved ENRIQUE MIRELES
Underground Mechanical 6/3/2024 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 6/10/2024 Approved ARTHUR NEGRETE
HVAC-Rough 6/10/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 6/10/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 6/12/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Approved ARTHUR NEGRETE
Gas Test 6/12/2024 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Rough 6/12/2024 Approved ARTHUR NEGRETE
Insulation 6/13/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 6/13/2024 Approved ARTHUR NEGRETE
Sewer 6/13/2024 Not Ready for Inspection ARTHUR NEGRETE
Drywall Nailing 6/17/2024 Approved ARTHUR NEGRETE
Shower Pan 6/17/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 6/21/2024 Approved JUSTIN HAWLEY
Sewer 6/21/2024 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 7/25/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 7/25/2024 Corrections Issued ANTHONY EGSON
Final 7/25/2024 Corrections Issued ANTHONY EGSON
Green Building Final 7/25/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 7/25/2024 Approved ANTHONY EGSON
HVAC-Final 7/25/2024 Corrections Issued ANTHONY EGSON
METHANE-Final 7/25/2024 Not Ready for Inspection ANTHONY EGSON
METHANE-Rough 7/25/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 7/25/2024 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 7/25/2024 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 7/25/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 8/5/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 8/5/2024 Approved ARTHUR NEGRETE
Final 8/5/2024 Partial Inspection ARTHUR NEGRETE
Green Building Final 8/5/2024 Approved ARTHUR NEGRETE
HVAC-Final 8/5/2024 Approved ARTHUR NEGRETE
METHANE-Final 8/5/2024 Approved ARTHUR NEGRETE
METHANE-Rough 8/5/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 8/5/2024 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 8/5/2024 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 8/5/2024 Approved ARTHUR NEGRETE
Final 8/14/2024 OK to Issue CofO ARTHUR NEGRETE