1434 1/4 S STANLEY AVE 90019
Certificate Information: 1434 1/4 S STANLEY AVE 90019
- Application / Permit
- 24016-10000-08614
- Plan Check / Job No.
- B24LA04602
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: Detached 1-Story Garage and Portion of Laundry Room Conversion to ADU per lamc 12.22 A.33 (c) and (d). All Work Done per WFPP.
- Permit Issued
- Issued on 5/16/2024
- Issuing Office
- Current Status
- CofO Issued on 11/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2024 | DAVID CASTILLO |
| Corrections Issued | 3/20/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 4/23/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 4/24/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 4/26/2024 | DAVID CASTILLO |
| Plan Check Approved | 5/6/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 5/7/2024 | REZA HAGHIGHAT |
| Issued | 5/16/2024 | APPLICANT |
| CofO in Progress | 8/16/2024 | ARTHUR NEGRETE |
| Permit Finaled | 11/21/2024 | DEROLD HAUFF |
| Permit Finaled | 11/21/2024 | DEROLD HAUFF |
| CofO Issued | 11/21/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/28/2024 | WALLIE JONG |
| Sewer availability | Cleared | 3/28/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2024 | WALLIE JONG |
Contact Information
| Contractor | E H D Builders Inc; Lic. No.: 1034101-B | 18375 VENTURA BLVD STE #122 TARZANA, CA 91356 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/20/2024 | Partial Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 5/28/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| METHANE-Barrier | 5/28/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| METHANE-Subgrade | 5/28/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Underground Mechanical | 5/28/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Deputy Drilled-In Anchors | 5/30/2024 | Conditional Approval | RICHARD DOCKUS |
| Special/Order Compliance | 5/30/2024 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 5/30/2024 | Partial Approval | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 6/3/2024 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 6/3/2024 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 6/3/2024 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 6/3/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/10/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 6/10/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 6/10/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 6/12/2024 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2024 | Approved | ARTHUR NEGRETE |
| Gas Test | 6/12/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Rough | 6/12/2024 | Approved | ARTHUR NEGRETE |
| Insulation | 6/13/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 6/13/2024 | Approved | ARTHUR NEGRETE |
| Sewer | 6/13/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Drywall Nailing | 6/17/2024 | Approved | ARTHUR NEGRETE |
| Shower Pan | 6/17/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 6/21/2024 | Approved | JUSTIN HAWLEY |
| Sewer | 6/21/2024 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 7/25/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 7/25/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 7/25/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 7/25/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 7/25/2024 | Approved | ANTHONY EGSON |
| HVAC-Final | 7/25/2024 | Corrections Issued | ANTHONY EGSON |
| METHANE-Final | 7/25/2024 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Rough | 7/25/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 7/25/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/25/2024 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 7/25/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/5/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 8/5/2024 | Approved | ARTHUR NEGRETE |
| Final | 8/5/2024 | Partial Inspection | ARTHUR NEGRETE |
| Green Building Final | 8/5/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 8/5/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Final | 8/5/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Rough | 8/5/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 8/5/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 8/5/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 8/5/2024 | Approved | ARTHUR NEGRETE |
| Final | 8/14/2024 | OK to Issue CofO | ARTHUR NEGRETE |