3706 S GREENFIELD AVE 90034

Certificate Information: 3706 S GREENFIELD AVE 90034

Application / Permit
24016-10000-08478
Plan Check / Job No.
B24LA04538
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Garage conversion and addition to create a new Accessory Dwelling Unit per State GC 66323(a)(2)
Permit Issued
Issued on 4/24/2025
Issuing Office
Current Status
Issued on 4/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/12/2024 APPLICANT
Assigned to Plan Check Engineer 3/15/2024 EDWIN ESPIN
Corrections Issued 3/18/2024 EDWIN ESPIN
Applicant returned to address corrections 1/30/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 2/21/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 3/16/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 4/16/2025 HOOMAN HAJIZADEH
Plan Check Approved 4/24/2025 ALFREDO JARA
Issued 4/24/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/25/2024 BRENDEN HAWK
Eng Process Fee Ord 176,300 Cleared 5/10/2024 BRENDEN HAWK
Sewer availability Cleared 5/10/2024 BRENDEN HAWK
Specific Plan Cleared 5/15/2024 JOSHUA JONES
Low Impact Development (LID) Cleared 12/4/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 2/13/2025 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 3/17/2025 EDWIN ESPIN
Grading Pre-Inspection Cleared 3/17/2025 EDWIN ESPIN

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/15/2025 Approved WILBER ROSALES
Excavation/Setback/Form/Re-Bar 7/18/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/31/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 9/2/2025 Approved KIRK SANDERS
PLUMBING-Rough 9/2/2025 Approved KIRK SANDERS
HVAC-Final 9/4/2025 Corrections Issued KIRK SANDERS
HVAC-Rough 9/4/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 9/5/2025 Partial Approval ARAM AVEDISIAN
HVAC-Rough 9/10/2025 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 10/9/2025 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 10/16/2025 Corrections Issued KIRK SANDERS
Green Building Rough 10/16/2025 Approved KIRK SANDERS
HVAC-Rough 10/16/2025 Partial Approval KIRK SANDERS
Verify Sprinkler Sign Off 10/16/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 10/20/2025 Approved MICHAEL ALLEN
HVAC-Rough 10/20/2025 Approved MICHAEL ALLEN
Insulation 10/24/2025 Approved KIRK SANDERS
Special/Order Compliance 10/24/2025 Corrections Issued KIRK SANDERS
Insulation 10/28/2025 Not Ready for Inspection KIRK SANDERS
Shower Pan 11/21/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 12/2/2025 Approved KIRK SANDERS
Special/Order Compliance 12/19/2025 Not Ready for Inspection KIRK SANDERS
Special/Order Compliance 12/22/2025 Approved KIRK SANDERS
Pre-Inspection 12/23/2025 Approved ANTHONY EGSON
Underground Mechanical 1/29/2026 Approved MICHAEL ALLEN
ELECTRICAL-Final 2/2/2026 Corrections Issued MICHAEL ALLEN
HVAC-Final 2/2/2026 Approved MICHAEL ALLEN
ELECTRICAL-Final 2/9/2026 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 2/9/2026 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 2/17/2026 Approved ANTHONY EGSON
PLUMBING-Final 2/17/2026 Approved ANTHONY EGSON
Drywall Nailing 4/1/2026 Approved RYAN SALAZAR
Final 4/1/2026 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 4/1/2026 Approved RYAN SALAZAR
Green Building Final 4/1/2026 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/1/2026 SGSOV Approved RYAN SALAZAR
Service/Power Release 4/1/2026 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 4/1/2026 Approved RYAN SALAZAR