1832 N AVENUE 52 90041

Certificate Information: 1832 N AVENUE 52 90041

Application / Permit
24016-10000-08115
Plan Check / Job No.
B24LA04324
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT A PORTION OF AN EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER CODE 65852.2(e)(1)(A) BECOMING AN ADU W/ ATTACHED ONE CAR GARAGE. "COMPLY WITH DEPARTMENT ORDER effective date 10/20/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 11/15/2024
Issuing Office
Current Status
CofO Issued on 4/1/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2024 APPLICANT
Assigned to Plan Check Engineer 3/21/2024 SERGIO GUTIERREZ
Corrections Issued 3/29/2024 SERGIO GUTIERREZ
Quality Review Completed 4/2/2024 RODOLFO ARIAS
Plan Check Approved 10/23/2024 SERGIO GUTIERREZ
Issued 11/15/2024 APPLICANT
CofO in Progress 3/6/2026 DANIEL DELACRUZ
Permit Finaled 4/1/2026 DANIEL SANCHEZ
CofO Issued 4/1/2026 DANIEL SANCHEZ
Permit Finaled 4/1/2026 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 4/5/2024 JESSICA OPINION
Roof/Waste drainage to street Cleared 4/5/2024 JESSICA OPINION
Street Frontage Cleared 4/5/2024 JESSICA OPINION
Hydrant and Access approval Cleared 5/5/2024 JOHN CONNEALLY
Grading Pre-Inspection Cleared 6/18/2024 LANNY MERRICK
Eng Process Fee Ord 176,300 Cleared 8/2/2024 JESSICA OPINION
Sewer availability Cleared 8/2/2024 JESSICA OPINION

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/30/2024 Partial Inspection DANIEL DELACRUZ
Footing/Foundation/Slab 10/20/2025 Approved DANIEL DELACRUZ
ELECTRICAL-Rough 11/12/2025 Not Ready for Inspection DANIEL DELACRUZ
Underground Mechanical 11/12/2025 Partial Approval DANIEL DELACRUZ
ELECTRICAL-Rough 11/24/2025 Approved DANIEL DELACRUZ
HVAC-Rough 11/24/2025 Approved DANIEL DELACRUZ
PLUMBING-Rough 11/24/2025 Approved DANIEL DELACRUZ
Underground Mechanical 11/24/2025 Approved DANIEL DELACRUZ
Insulation 11/25/2025 Approved DANIEL DELACRUZ
BUILDING-Rough-Frame 12/2/2025 Approved DANIEL DELACRUZ
Floor/Roof Diaphrgm/Shear Wall 12/2/2025 Approved DANIEL DELACRUZ
Interior/Exterior Lathing 12/2/2025 Approved DANIEL DELACRUZ
Drywall Nailing 12/12/2025 Approved DANIEL DELACRUZ
Gas Test 12/16/2025 Not Ready for Inspection DANIEL DELACRUZ
ELECTRICAL-Final 2/6/2026 Approved DANIEL DELACRUZ
Final 2/6/2026 Not Ready for Inspection DANIEL DELACRUZ
HVAC-Final 2/6/2026 Approved DANIEL DELACRUZ
PLUMBING-Final 2/6/2026 Corrections Issued DANIEL DELACRUZ
Smoke Detectors 2/6/2026 Approved DANIEL DELACRUZ
Final 3/6/2026 OK to Issue CofO DANIEL DELACRUZ
Gas Test 3/6/2026 Approved DANIEL DELACRUZ
PLUMBING-Final 3/6/2026 Approved DANIEL DELACRUZ