2343 W LAS COLINAS AVE 90041
Certificate Information: 2343 W LAS COLINAS AVE 90041
- Application / Permit
- 24016-10000-07831
- Plan Check / Job No.
- B24LA04128
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan REMODEL KITCHEN AND MASTER BEDROOM AND BATH IN (E) SFD WITH ADDITION OF (N) UNCOVERED DECK AT REAR
- Permit Issued
- Issued on 4/25/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/21/2025
Permit Application Status History
| Submitted | 3/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2024 | MINA HABILI |
| Corrections Issued | 3/8/2024 | MINA HABILI |
| Applicant returned to address corrections | 4/3/2024 | LAWRENCE QUIRANTE |
| Plan Check Approved | 4/25/2024 | MINA HABILI |
| Issued | 4/25/2024 | APPLICANT |
| Permit Finaled | 8/20/2025 | ALIZAH MAYAGOITIA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/25/2024 | MINA HABILI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hanna,, Emil Ramzy; Lic. No.: C63602 | 18925 GRANADA CIRCLE NORTHRIDGE, CA 91326 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/30/2024 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/4/2024 | Approved | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 7/17/2024 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/22/2024 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/22/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/22/2024 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/22/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 8/29/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/29/2024 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 9/4/2024 | Partial Approval | LUIS CASTRO |
| Shower Pan | 9/4/2024 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 9/17/2024 | Approved | ROY SPAULDING |
| Final | 3/24/2025 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/24/2025 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 3/24/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/4/2025 | No Access for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Final | 8/20/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/20/2025 | Permit Finaled | ALIZAH MAYAGOITIA |