eplan REMODEL KITCHEN AND MASTER BEDROOM AND BATH IN (E) SFD WITH ADDITION OF (N) UNCOVERED DECK AT REAR
Permit Issued
Issued on 4/25/2024
Issuing Office
Current Status
Permit Finaled on 8/21/2025

Permit Application Status History

Submitted 3/6/2024 APPLICANT
Assigned to Plan Check Engineer 3/8/2024 MINA HABILI
Corrections Issued 3/8/2024 MINA HABILI
Applicant returned to address corrections 4/3/2024 LAWRENCE QUIRANTE
Plan Check Approved 4/25/2024 MINA HABILI
Issued 4/25/2024 APPLICANT
Permit Finaled 8/20/2025 ALIZAH MAYAGOITIA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/25/2024 MINA HABILI

Contact Information

Contractor Owner-Builder       ,
Engineer Hanna,, Emil Ramzy; Lic. No.: C63602 18925 GRANADA CIRCLE      NORTHRIDGE, CA 91326

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/30/2024 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 6/4/2024 Approved CRAIG VAUGHAN
Deputy Drilled-In Anchors 7/17/2024 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 8/22/2024 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 8/22/2024 Approved CRAIG VAUGHAN
HVAC-Rough 8/22/2024 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 8/22/2024 Approved CRAIG VAUGHAN
Insulation 8/29/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/29/2024 Partial Approval CRAIG VAUGHAN
Drywall Nailing 9/4/2024 Partial Approval LUIS CASTRO
Shower Pan 9/4/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 9/17/2024 Approved ROY SPAULDING
Final 3/24/2025 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/24/2025 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 3/24/2025 Approved LILIANA PORTILLO
ELECTRICAL-Rough 4/4/2025 No Access for Inspection DAVID WILLIAMS
ELECTRICAL-Final 8/20/2025 Approved ALIZAH MAYAGOITIA
Final 8/20/2025 Permit Finaled ALIZAH MAYAGOITIA