3781 S WADE ST 90066

Certificate Information: 3781 S WADE ST 90066

Application / Permit
24016-10000-07462
Plan Check / Job No.
B24LA03921
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert Existing Detached Garage and Storage to New Accessory Dwelling Unit per GCS 65852.2(e)(1)(A). "COMPLY WITH DEPARTMENT ORDER effective date 02/01/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 6/18/2024
Issuing Office
Current Status
CofO Issued on 6/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2024 APPLICANT
Assigned to Plan Check Engineer 3/7/2024 ALEC MOUSAKHANIAN
Corrections Issued 3/8/2024 ALEC MOUSAKHANIAN
Plan Check Approved 4/24/2024 ALEC MOUSAKHANIAN
Issued 6/18/2024 APPLICANT
Permit Finaled 6/4/2025 CLAUDIO MORENO
CofO Issued 6/4/2025 CLAUDIO MORENO
Permit Finaled 6/4/2025 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 3/26/2024 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 3/26/2024 KIMBERLY HERNANDEZ
Sewer availability Cleared 3/26/2024 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 4/10/2024 KIMBERLY HERNANDEZ
Grading Pre-Inspection Cleared 4/18/2024 VASIL MIHALEV

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/29/2024 Not Ready for Inspection RYAN BARNES
Final 7/29/2024 Not Ready for Inspection RYAN BARNES
Green Building Final 7/29/2024 Not Ready for Inspection RYAN BARNES
Green Building Rough 7/29/2024 Not Ready for Inspection RYAN BARNES
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Not Ready RYAN BARNES
Smoke Detectors 7/29/2024 Not Ready for Inspection RYAN BARNES
ELECTRICAL-Rough 8/28/2024 Not Ready for Inspection RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Approved RYAN BARNES
Footing/Foundation/Slab 8/28/2024 Not Ready for Inspection RYAN BARNES
Drywall Nailing 8/30/2024 Partial Approval RYAN BARNES
ELECTRICAL-Rough 8/30/2024 Partial Approval RYAN BARNES
Footing/Foundation/Slab 8/30/2024 Not Ready for Inspection RYAN BARNES
Excavation/Setback/Form/Re-Bar 9/17/2024 Approved RYAN BARNES
ELECTRICAL-Final 11/12/2024 Not Ready for Inspection RYAN BARNES
ELECTRICAL-Rough 11/12/2024 Approved RYAN BARNES
BUILDING-Rough-Frame 12/2/2024 Approved RYAN BARNES
Green Building Rough 12/2/2024 Approved RYAN BARNES
HVAC-Rough 12/2/2024 Approved RYAN BARNES
PLUMBING-Rough 12/2/2024 Approved RYAN BARNES
Drywall Nailing 12/6/2024 Approved RYAN BARNES
Final 12/30/2024 Conditional Approval RYAN BARNES
Green Building Final 12/30/2024 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Approved RYAN BARNES
Smoke Detectors 12/30/2024 Approved RYAN BARNES