3230 S OVERLAND AVE 90034

Certificate Information: 3230 S OVERLAND AVE 90034

Application / Permit
24016-10000-07431
Plan Check / Job No.
B23LA24883
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
eplan foundation repair of (e) foundation pad ( 46 location )
Permit Issued
Issued on 6/3/2024
Issuing Office
Current Status
Issued on 6/3/2024

Permit Application Status History

Submitted 3/5/2024 APPLICANT
Assigned to Plan Check Engineer 3/8/2024 MOHAMMAD ESMAILI
Corrections Issued 3/8/2024 MOHAMMAD ESMAILI
Plan Check Approved 4/7/2024 MOHAMMAD ESMAILI
Issued 6/3/2024 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 3/28/2024 RICARDO BOHORQUEZ
Grading Pre-Inspection Cleared 4/1/2024 VASIL MIHALEV
Miscellaneous Cleared 4/4/2024 VARAND SARKISIAN

Contact Information

Contractor Collaborative Construction Inc; Lic. No.: 956472-B       ,
Contractor Peter Terpinski; Lic. No.: 956472-B       ,
Engineer Coray,, Jason Gregory; Lic. No.: S4926 56 OAK SPRINGS DR      SAN ANSELMO, CA 94930

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/18/2025 Approved FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 6/20/2025 Partial Approval FARHAD DADBIN
Footing/Foundation/Slab 10/10/2025 Partial Approval FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 5/28/2026 Partial Approval FARHAD DADBIN