6081 W CENTER DR 90045
Certificate Information: 6081 W CENTER DR 90045
- Application / Permit
- 24016-10000-07399
- Plan Check / Job No.
- B24LA03866
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (4) Amusement Enterprises
- Work Description
- TENANT IMPROVEMENT AND CHANGE OF USE TO CREATE A SHELL SPACE FOR A FUTURE IMMERSIVE ART MUSEUM IN AN EXISTING MOVIE THEATER SPACE.
- Permit Issued
- Issued on 9/24/2024
- Issuing Office
- Current Status
- Issued on 9/24/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | HERNAN ARREOLA |
| Assigned to Zoning Architect | 3/7/2024 | HERNAN ARREOLA |
| Corrections Issued | 3/18/2024 | HERNAN ARREOLA |
| Quality Review Completed | 3/19/2024 | PETER KIM |
| Applicant returned to address corrections | 6/17/2024 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/11/2024 | HERNAN ARREOLA |
| Plan Check Approved | 8/12/2024 | HERNAN ARREOLA |
| Issued | 9/24/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/1/2024 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2024 | DINAH GARIN |
| ZA Case | Cleared | 4/8/2024 | MATHEW QUAN |
| ZA Case | Cleared | 4/8/2024 | MATHEW QUAN |
| Specific Plan | Cleared | 5/20/2024 | PEDRO AYALA |
| Highway dedication | Cleared | 6/4/2024 | DINAH GARIN |
| DAS Clearance | Cleared | 6/24/2024 | Fernando Flores |
| Address approval | Cleared | 6/25/2024 | ANTHONY MAINEZ |
| Green Code | Cleared | 6/25/2024 | DONALD CRICHLOW |
| Fire Marshal Fire Life Safety | Cleared | 7/10/2024 | MENOA AGHAJANI |
| Zoning Plan Check | Cleared | 7/31/2024 | Fernando Flores |
Contact Information
| Architect | Bruce,, Thomas A; Lic. No.: C31251 | 1837 N WILTON PL 6 LOS ANGELES, CA 90028 |
| Contractor | Mata Contracting Corporation; Lic. No.: 966590-B | , |
| Contractor | Om Construction; Lic. No.: 966590-B | , |
| Engineer | Garza,, Omar Leonel; Lic. No.: S5593 | 5050 EAGLE ROCK BOULEVARD LOS ANGELES, CA 90041 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 10/25/2024 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 10/31/2024 | Partial Approval | GRANT WOODS |
| Deputy Steel/Welding | 12/16/2024 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 12/18/2024 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 12/19/2024 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 12/20/2024 | Conditional Approval | GRANT WOODS |
| Light Gage Steel Frame | 12/30/2024 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 1/3/2025 | Partial Approval | GRANT WOODS |
| Deputy Steel/Welding | 1/10/2025 | Conditional Approval | GRANT WOODS |
| Light Gage Steel Frame | 1/14/2025 | Partial Approval | ALAN NOVAK |
| Drywall Nailing | 1/28/2025 | Not Ready for Inspection | GRANT WOODS |
| Deputy Steel/Welding | 1/31/2025 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 2/11/2025 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 3/3/2025 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 3/6/2025 | Approved | GRANT WOODS |
| Deputy Steel/Welding | 3/13/2025 | Conditional Approval | GRANT WOODS |
| Drywall Nailing | 3/28/2025 | Approved | VASIL MIHALEV |
| Light Gage Steel Frame | 4/2/2025 | Approved | MICHAEL PETRUSKO |
| Deputy Steel/Welding | 4/3/2025 | Conditional Approval | VASIL MIHALEV |
| Drywall Nailing | 4/3/2025 | Approved | VASIL MIHALEV |
| Deputy Steel/Welding | 4/8/2025 | Approved | VASIL MIHALEV |
| Light Gage Steel Frame | 4/8/2025 | Approved | VASIL MIHALEV |
| Structural Steel Frame | 4/8/2025 | Approved | VASIL MIHALEV |
| Deputy Steel/Welding | 4/9/2025 | Conditional Approval | RICARDO ROBLES |
| Drywall Nailing | 4/9/2025 | Partial Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 4/24/2025 | Partial Approval | VASIL MIHALEV |
| Structural Steel Frame | 4/25/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Deputy Fireproofing | 4/28/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 4/28/2025 | Conditional Approval | RICARDO ROBLES |
| Structural Steel Frame | 4/28/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 4/29/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Fireproofing | 4/30/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 4/30/2025 | Conditional Approval | RICARDO ROBLES |
| Structural Steel Frame | 4/30/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Fireproofing | 5/1/2025 | Approved | VASIL MIHALEV |
| Deputy Drilled-In Anchors | 5/2/2025 | Conditional Approval | GRANT WOODS |
| Deputy Fireproofing | 5/2/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Reinf. Concrete | 5/2/2025 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 5/2/2025 | Partial Approval | DAVID TSAU |
| Deputy Fireproofing | 5/5/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 5/6/2025 | Conditional Approval | DAVID TSAU |
| Deputy Fireproofing | 5/7/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Fireproofing | 5/8/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 5/9/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 5/12/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 5/13/2025 | No Access for Inspection | VASIL MIHALEV |
| Deputy Fireproofing | 5/14/2025 | Approved | DERRICK SPENCER |
| T-Bar Ceiling | 5/14/2025 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 5/15/2025 | Conditional Approval | GRANT WOODS |
| Deputy Fireproofing | 5/15/2025 | Approved | VASIL MIHALEV |
| Deputy Reinf. Concrete | 5/15/2025 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 5/16/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Fireproofing | 5/16/2025 | Conditional Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 5/16/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Excavation/Setback/Form/Re-Bar | 5/16/2025 | Partial Approval | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 5/19/2025 | Conditional Approval | GRANT WOODS |
| Deputy Fireproofing | 5/19/2025 | Approved | VASIL MIHALEV |
| Deputy Reinf. Concrete | 5/19/2025 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 5/19/2025 | Conditional Approval | VASIL MIHALEV |
| Structural Steel Frame | 5/19/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 5/20/2025 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/20/2025 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 5/20/2025 | Partial Approval | DERRICK SPENCER |
| Deputy Fireproofing | 5/21/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 5/22/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Fireproofing | 5/23/2025 | No Access for Inspection | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/23/2025 | Conditional Approval | GRANT WOODS |
| Light Gage Steel Frame | 5/23/2025 | No Access for Inspection | DERRICK SPENCER |
| Deputy Fireproofing | 5/27/2025 | Partial Approval | VASIL MIHALEV |
| Light Gage Steel Frame | 5/27/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 5/28/2025 | Conditional Approval | RICARDO ROBLES |
| Drywall Nailing | 5/28/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 5/28/2025 | Partial Approval | RICARDO ROBLES |
| Deputy Fireproofing | 5/29/2025 | No Access for Inspection | VASIL MIHALEV |
| Drywall Nailing | 5/29/2025 | Approved | VASIL MIHALEV |
| Insulation | 5/29/2025 | Approved | VASIL MIHALEV |
| Light Gage Steel Frame | 5/29/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 5/30/2025 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 5/30/2025 | Partial Approval | JOEY BUCHANAN |
| Light Gage Steel Frame | 5/30/2025 | Partial Approval | JOEY BUCHANAN |
| Deputy Fireproofing | 6/2/2025 | Conditional Approval | RICARDO ROBLES |
| Structural Steel Frame | 6/2/2025 | Partial Approval | RICARDO ROBLES |
| Deputy Fireproofing | 6/3/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 6/4/2025 | Conditional Approval | VASIL MIHALEV |
| Deputy Fireproofing | 6/5/2025 | No Access for Inspection | VASIL MIHALEV |
| Deputy Steel/Welding | 6/5/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 6/6/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 6/9/2025 | Conditional Approval | GRANT WOODS |
| Deputy Fireproofing | 6/10/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 6/11/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 6/12/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Light Gage Steel Frame | 6/12/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Deputy Fireproofing | 6/13/2025 | No Access for Inspection | VASIL MIHALEV |
| Deputy Reinf. Concrete | 6/13/2025 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 6/13/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 6/16/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Steel/Welding | 6/16/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 6/17/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 6/18/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 6/20/2025 | Approved | DERRICK SPENCER |
| Deputy Fireproofing | 6/23/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Fireproofing | 6/25/2025 | Approved | DERRICK SPENCER |
| Deputy Fireproofing | 6/26/2025 | Approved | DERRICK SPENCER |
| Structural Steel Frame | 6/26/2025 | Partial Approval | DERRICK SPENCER |
| Deputy Fireproofing | 6/27/2025 | Approved | DERRICK SPENCER |
| Deputy Fireproofing | 6/30/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Fireproofing | 6/30/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Fireproofing | 7/1/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Fireproofing | 7/2/2025 | Conditional Approval | GRANT WOODS |
| Deputy Fireproofing | 7/3/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Structural Steel Frame | 7/9/2025 | Partial Approval | DERRICK SPENCER |
| Deputy Fireproofing | 7/10/2025 | Conditional Approval | GRANT WOODS |
| Deputy Fireproofing | 7/14/2025 | Conditional Approval | GRANT WOODS |
| Deputy Fireproofing | 7/15/2025 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 7/22/2025 | Conditional Approval | CASIMIR BRITTON |
| Deputy Reinf. Concrete | 8/7/2025 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 8/7/2025 | Approved | VASIL MIHALEV |
| Deputy Reinf. Concrete | 8/8/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 8/11/2025 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 8/11/2025 | Conditional Approval | GRANT WOODS |
| Structural Steel Frame | 8/11/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 8/12/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 8/13/2025 | Approved | VASIL MIHALEV |
| Structural Steel Frame | 8/13/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 8/14/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 8/15/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 8/18/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 8/19/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Steel/Welding | 8/19/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 8/20/2025 | Approved | VASIL MIHALEV |
| Light Gage Steel Frame | 8/20/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 8/21/2025 | Approved | VASIL MIHALEV |
| Light Gage Steel Frame | 8/21/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 8/22/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Steel/Welding | 8/22/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Drilled-In Anchors | 8/25/2025 | Conditional Approval | GRANT WOODS |
| Deputy Fireproofing | 8/25/2025 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 8/25/2025 | Approved | VASIL MIHALEV |
| Light Gage Steel Frame | 8/25/2025 | Approved | VASIL MIHALEV |
| Deputy Drilled-In Anchors | 8/26/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 8/26/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Reinf. Concrete | 8/26/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Drilled-In Anchors | 8/27/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 8/27/2025 | Approved | VASIL MIHALEV |
| Deputy Reinf. Concrete | 8/27/2025 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 8/27/2025 | Approved | VASIL MIHALEV |
| Deputy Drilled-In Anchors | 8/28/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 8/28/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Reinf. Concrete | 8/28/2025 | Approved | VASIL MIHALEV |
| Deputy Fireproofing | 8/29/2025 | Approved | NICK LAROCCA |
| Deputy Fireproofing | 9/2/2025 | Partial Approval | VASIL MIHALEV |
| Light Gage Steel Frame | 9/4/2025 | Approved | VASIL MIHALEV |
| Light Gage Steel Frame | 9/5/2025 | Approved | VASIL MIHALEV |
| Deputy Steel/Welding | 9/9/2025 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 9/10/2025 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 9/10/2025 | Conditional Approval | GRANT WOODS |
| Drywall Nailing | 9/10/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Light Gage Steel Frame | 9/10/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Structural Steel Frame | 9/10/2025 | Approved | MICHAEL PETRUSKO |
| Deputy Drilled-In Anchors | 9/11/2025 | Approved | VASIL MIHALEV |
| Deputy Reinf. Concrete | 9/11/2025 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 9/11/2025 | Approved | VASIL MIHALEV |
| Deputy Drilled-In Anchors | 9/12/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Reinf. Concrete | 9/12/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Fireproofing | 9/15/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Fireproofing | 9/16/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Fireproofing | 9/17/2025 | Partial Approval | VASIL MIHALEV |
| Light Gage Steel Frame | 10/2/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Deputy Drilled-In Anchors | 11/18/2025 | Partial Approval | VASIL MIHALEV |
| Light Gage Steel Frame | 12/8/2025 | Partial Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 12/18/2025 | Partial Approval | VASIL MIHALEV |
| Light Gage Steel Frame | 1/26/2026 | Not Ready for Inspection | ROGELIO REYNA |
| Deputy Drilled-In Anchors | 2/3/2026 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 2/3/2026 | Approved | DERRICK SPENCER |