4042 E BAYWOOD ST 90039

Certificate Information: 4042 E BAYWOOD ST 90039

Application / Permit
24016-10000-06770
Plan Check / Job No.
B24LA03686
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
***ePlan*** Convert (e) det. garage to an ADU per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 8/6/2024
Issuing Office
Current Status
CofO Issued on 3/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2024 APPLICANT
Assigned to Plan Check Engineer 3/1/2024 LUISANGEL VALENZUELA
Corrections Issued 3/2/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 4/12/2024 LUISANGEL VALENZUELA
Plan Check Approved 4/17/2024 ARAMIK SHAHMIRZAIAN
Issued 8/6/2024 APPLICANT
CofO in Progress 3/18/2025 NICHOLAS LOPEZ
Permit Finaled 3/20/2025 DEROLD HAUFF
CofO Issued 3/20/2025 DEROLD HAUFF
Permit Finaled 3/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/8/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 4/15/2024 JESSICA OPINION
Sewer availability Cleared 4/15/2024 JESSICA OPINION

Contact Information

Contractor Lae Construction Inc; Lic. No.: 1068365-B       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/16/2024 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 9/27/2024 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 9/27/2024 Partial Approval THOMAS LOGRASSO
Sewer 9/27/2024 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 10/7/2024 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 10/10/2024 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 12/4/2024 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 12/4/2024 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 12/10/2024 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 12/10/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 12/17/2024 Conditional Approval THOMAS LOGRASSO
Green Building Rough 12/17/2024 Approved THOMAS LOGRASSO
Insulation 12/17/2024 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 12/17/2024 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 12/17/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 12/27/2024 Approved THOMAS LOGRASSO
Drywall Nailing 12/27/2024 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 12/27/2024 Approved THOMAS LOGRASSO
Insulation 12/27/2024 Approved THOMAS LOGRASSO
Drywall Nailing 1/7/2025 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 1/7/2025 Approved CRAIG DAVIS
Drywall Nailing 3/5/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 3/5/2025 Corrections Issued NICHOLAS LOPEZ
Final 3/5/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 3/5/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 3/5/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 3/5/2025 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV No Gas NICHOLAS LOPEZ
Smoke Detectors 3/5/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 3/12/2025 Approved NICHOLAS LOPEZ
Final 3/12/2025 Not Ready for Inspection NICHOLAS LOPEZ
Green Building Final 3/12/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 3/12/2025 Not Ready for Inspection NICHOLAS LOPEZ
PLUMBING-Final 3/12/2025 Approved NICHOLAS LOPEZ
Final 3/18/2025 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 3/18/2025 Approved NICHOLAS LOPEZ
HVAC-Final 3/18/2025 Approved NICHOLAS LOPEZ