4042 E BAYWOOD ST 90039
Certificate Information: 4042 E BAYWOOD ST 90039
- Application / Permit
- 24016-10000-06770
- Plan Check / Job No.
- B24LA03686
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ***ePlan*** Convert (e) det. garage to an ADU per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- Current Status
- CofO Issued on 3/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 3/2/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 4/12/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/17/2024 | ARAMIK SHAHMIRZAIAN |
| Issued | 8/6/2024 | APPLICANT |
| CofO in Progress | 3/18/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
| CofO Issued | 3/20/2025 | DEROLD HAUFF |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 4/15/2024 | JESSICA OPINION |
Contact Information
| Contractor | Lae Construction Inc; Lic. No.: 1068365-B | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/16/2024 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/27/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 9/27/2024 | Partial Approval | THOMAS LOGRASSO |
| Sewer | 9/27/2024 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/7/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/10/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 12/4/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/4/2024 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 12/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/17/2024 | Conditional Approval | THOMAS LOGRASSO |
| Green Building Rough | 12/17/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 12/17/2024 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/17/2024 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/17/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/27/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 12/27/2024 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 12/27/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 12/27/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 1/7/2025 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 1/7/2025 | Approved | CRAIG DAVIS |
| Drywall Nailing | 3/5/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 3/5/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 3/5/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 3/5/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 3/5/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 3/5/2025 | Corrections Issued | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/5/2025 | SGSOV No Gas | NICHOLAS LOPEZ |
| Smoke Detectors | 3/5/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 3/12/2025 | Approved | NICHOLAS LOPEZ |
| Final | 3/12/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Green Building Final | 3/12/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 3/12/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| PLUMBING-Final | 3/12/2025 | Approved | NICHOLAS LOPEZ |
| Final | 3/18/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 3/18/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Final | 3/18/2025 | Approved | NICHOLAS LOPEZ |