15019 W DICKENS ST 91403
Certificate Information: 15019 W DICKENS ST 91403
- Application / Permit
- 24016-10000-06542
- Plan Check / Job No.
- B24LA03537
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** Conversion of Portion of (E) dettached Garage to an Accessory Dwelling Unit per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/25/2024
- Issuing Office
- Current Status
- CofO Issued on 1/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2024 | DAVID CASTILLO |
| Corrections Issued | 3/7/2024 | DAVID CASTILLO |
| Plan Check Approved | 3/26/2024 | EDWIN ESPIN |
| Issued | 4/25/2024 | APPLICANT |
| CofO in Progress | 1/10/2025 | BRIAN KELLY |
| Permit Finaled | 1/10/2025 | JEFFREY DURAN |
| CofO Issued | 1/10/2025 | JEFFREY DURAN |
| Permit Finaled | 1/10/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/12/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/14/2024 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 3/15/2024 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/8/2024 | Conditional Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 5/8/2024 | Partial Inspection | BRIAN KELLY |
| PLUMBING-Rough | 5/8/2024 | No Access for Inspection | BRIAN KELLY |
| Special/Order Compliance | 5/13/2024 | Partial Inspection | BRIAN KELLY |
| Special/Order Compliance | 5/14/2024 | Partial Inspection | BRIAN KELLY |
| Wood Frame | 5/23/2024 | Partial Inspection | BRIAN KELLY |
| Deputy Wood Construction | 5/24/2024 | Conditional Approval | BRIAN KELLY |
| Interior/Exterior Lathing | 5/29/2024 | Corrections Issued | BRIAN KELLY |
| Interior/Exterior Lathing | 6/6/2024 | Partial Approval | ROBERT DAVIS |
| Wood Frame | 6/24/2024 | Partial Inspection | ANDREW DORSO |
| Insulation | 6/28/2024 | Approved | ANDREW DORSO |
| Wood Frame | 7/2/2024 | Approved | BRIAN KELLY |
| Drywall Nailing | 7/11/2024 | Not Ready for Inspection | BRIAN KELLY |
| Drywall Nailing | 7/15/2024 | Approved | BRIAN KELLY |
| BUILDING-Rough-Frame | 10/15/2024 | Approved | BRIAN KELLY |
| Final | 10/15/2024 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 10/15/2024 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Rough | 10/15/2024 | Approved | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 10/15/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 1/6/2025 | OK to Issue CofO | BRIAN KELLY |
| Green Building Final | 1/6/2025 | Approved | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 1/6/2025 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 1/6/2025 | Approved | BRIAN KELLY |