713-715 1/2 E SUNSET AVE 90291
Certificate Information: 713-715 1/2 E SUNSET AVE 90291
- Application / Permit
- 24016-10000-06422
- Plan Check / Job No.
- B24LA03464
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT PORTION OF (E) DUPLEX (408 SF) TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e).
- Permit Issued
- Issued on 4/22/2026
- Issuing Office
- Current Status
- Issued on 4/22/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2024 | KAMYAR EMAMI |
| Corrections Issued | 3/4/2024 | KAMYAR EMAMI |
| Applicant returned to address corrections | 5/22/2024 | KAMYAR EMAMI |
| Applicant returned to address corrections | 4/14/2026 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 4/20/2026 | GIOVANNY CHAVEZ |
| Plan Check Approved | 4/22/2026 | GIOVANNY CHAVEZ |
| Issued | 4/22/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/8/2024 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 5/8/2024 | VLADIMIR ARUTYUNYAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2024 | VLADIMIR ARUTYUNYAN |
| Specific Plan | Cleared | 6/3/2024 | FREDDY GARCIA |
| Specific Plan | Cleared | 6/3/2024 | FREDDY GARCIA |
| Miscellaneous | Cleared | 10/15/2024 | DAVID URITA |
| Miscellaneous | Cleared | 10/15/2024 | DAVID URITA |
| Miscellaneous | Cleared | 10/15/2024 | DAVID URITA |
| Coastal Zone | Cleared | 4/9/2026 | RUBEN VASQUEZ |
| Specific Plan | Cleared | 4/9/2026 | RUBEN VASQUEZ |
| Specific Plan | Cleared | 4/9/2026 | RUBEN VASQUEZ |
| ZI | Cleared | 4/9/2026 | RUBEN VASQUEZ |
Contact Information
| Architect | Kyurkchieva,, Savina; Lic. No.: NA39850 | , |
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 3000 E. BIRCH ST SUITE 201 BREA, CA 92821 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/30/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Footing/Foundation/Slab | 5/1/2026 | Corrections Issued | RUBEN RIVAS |
| BUILDING-Rough-Frame | 5/6/2026 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Rough | 5/6/2026 | Corrections Issued | RUBEN RIVAS |
| Footing/Foundation/Slab | 5/6/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 5/6/2026 | Approved | RUBEN RIVAS |
| Insulation | 5/12/2026 | Approved | RUBEN RIVAS |
| Wood Frame | 5/12/2026 | Approved | RUBEN RIVAS |