14006 W RIVERSIDE DR 26 91423
Certificate Information: 14006 W RIVERSIDE DR 26 91423
- Application / Permit
- 24016-10000-06384
- Plan Check / Job No.
- B24LA03444
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Tenant Improvement in a newly built core & shell space ( restaurant )
- Permit Issued
- Issued on 9/10/2024
- Issuing Office
- Current Status
- Issued on 9/10/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/29/2024 | GEORGE JOLAKIAN |
| Assigned to Zoning Architect | 2/29/2024 | GEORGE JOLAKIAN |
| Corrections Issued | 4/4/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 4/16/2024 | RODOLFO ARIAS |
| Plan Check Approved | 8/6/2024 | GEORGE JOLAKIAN |
| No Progress | 8/13/2024 | GEORGE JOLAKIAN |
| Plan Check Approved | 9/5/2024 | GEORGE JOLAKIAN |
| Issued | 9/10/2024 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/9/2024 | BRENNEN OBETO |
| CPC | Cleared | 4/9/2024 | BRENNEN OBETO |
| ZA Case | Cleared | 4/9/2024 | BRENNEN OBETO |
| Sewer availability | Cleared | 4/12/2024 | KENIA CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2024 | KENIA CASTILLO |
| Hydrant and Access approval | Cleared | 5/9/2024 | KURT CORRAL |
| Green Code | Cleared | 5/16/2024 | Luke Gonzales |
| Food Service Establishment | Cleared | 6/5/2024 | CRYSTOL BRANDT |
| DAS Clearance | Cleared | 6/10/2024 | Luke Gonzales |
| Food establishment approval | Cleared | 7/30/2024 | LACDHS APPROVED |
| Zoning Plan Check | Cleared | 7/30/2024 | Luke Gonzales |
Contact Information
| Contractor | Zen Construction Inc; Lic. No.: 1020397-B | , |
| Engineer | Chen,, Junfei; Lic. No.: NA85841 | , |
| Engineer | Yu,, Man Chiu; Lic. No.: S2588 | 2358 NOGALES ST ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 7/15/2026 |
| Footing/Foundation/Slab | 7/15/2026 |
| SGSOV-Seismic Gas S/O Valve | 7/15/2026 |
| Green Building Final | 7/15/2026 |
| Reinforced Concrete Frame | 7/15/2026 |
Inspection Request History
| Deputy Drilled-In Anchors | 11/12/2024 | Conditional Approval | STEVEN LEVITT |
| Footing/Foundation/Slab | 11/13/2024 | Approved | STEVEN LEVITT |
| Green Building Rough | 4/2/2025 | Approved | KENNETH ROBERTS |
| Reinforced Concrete Frame | 4/2/2025 | Partial Approval | KENNETH ROBERTS |
| Special/Order Compliance | 4/2/2025 | Approved | KENNETH ROBERTS |
| Footing/Foundation/Slab | 5/23/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 6/11/2025 | Partial Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 6/20/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 6/20/2025 | Approved | DEANDRE HOFFMAN |
| Deputy Steel/Welding | 6/23/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Structural Steel Frame | 6/27/2025 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 6/30/2025 | Approved | ANDREW DORSO |
| Footing/Foundation/Slab | 3/16/2026 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Green Building Final | 3/16/2026 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Reinforced Concrete Frame | 3/16/2026 | Not Ready for Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Not Ready | DEANDRE HOFFMAN |
| Smoke Detectors | 3/16/2026 | Approved | DEANDRE HOFFMAN |