303 S UNION AVE 90017
Certificate Information: 303 S UNION AVE 90017
- Application / Permit
- 24016-10000-06349
- Plan Check / Job No.
- B24LA03420
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Clinic
- Work Description
- **EPLAN CHANGE OF USE OF (E) TWO STORY TYPE I-B OFFICE BUILDING TO ADULT DAY CARE CENTER ( I-4 OCCUPANCY) & MEDICAL CLINIC OCHPD 3 ( HCAI 3) & INTERIOR T.I.
- Permit Issued
- Issued on 8/28/2024
- Issuing Office
- Current Status
- CofO Issued on 1/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/29/2024 | GARO TELMI |
| Assigned to Zoning Architect | 2/29/2024 | GARO TELMI |
| Corrections Issued | 3/5/2024 | GARO TELMI |
| Quality Review Completed | 3/28/2024 | CHAD DOI |
| Applicant returned to address corrections | 6/18/2024 | GARO TELMI |
| Applicant returned to address corrections | 8/20/2024 | GARO TELMI |
| Plan Check Approved | 8/28/2024 | GARO TELMI |
| Issued | 8/28/2024 | APPLICANT |
| CofO in Progress | 1/31/2025 | LUIS CCAMACHO |
| Permit Finaled | 1/31/2025 | ERNESTO CORRAL |
| CofO Issued | 1/31/2025 | ERNESTO CORRAL |
| Permit Finaled | 1/31/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 3/28/2024 | Cristina Salazar |
| Historic Resource Verification | Cleared | 4/8/2024 | ELIZABETH GALLARDO |
| Redevelopment Project Area | Cleared | 4/8/2024 | ELIZABETH GALLARDO |
| Address approval | Cleared | 7/10/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2024 | CELINA MORENO |
| Sewer availability | Cleared | 7/10/2024 | CELINA MORENO |
| DAS Clearance | Cleared | 8/7/2024 | Cristina Salazar |
| Food establishment approval | Cleared | 8/20/2024 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 8/23/2024 | PAWAN VERMA |
| Fire Marshal Fire Life Safety | Cleared | 8/28/2024 | WILLIAM JOHNS |
| Zoning Plan Check | Cleared | 8/28/2024 | Cristina Salazar |
Contact Information
| Architect | Morris,, Peter Lloyd; Lic. No.: NA32096 | , |
| Contractor | Sheene Paul Corporation; Lic. No.: 1015399-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 8/30/2024 | Partial Approval | MARTIN TAVITIAN |
| Light Gage Steel Frame | 8/30/2024 | Partial Approval | TIMOTHY POWELL |
| T-Bar Ceiling | 8/30/2024 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 8/31/2024 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 8/31/2024 | Partial Approval | JEROME BLACKWOOD |
| T-Bar Ceiling | 8/31/2024 | Partial Approval | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | MARTIN TAVITIAN |
| Pre-Inspection | 1/28/2025 | Partial Approval | LUIS CCAMACHO |
| Final | 1/31/2025 | OK to Issue CofO | LUIS CCAMACHO |
| Green Building Final | 1/31/2025 | Approved | LUIS CCAMACHO |
| Green Building Rough | 1/31/2025 | Approved | LUIS CCAMACHO |
| METHANE-Final | 1/31/2025 | Approved | LUIS CCAMACHO |
| METHANE-Rough | 1/31/2025 | Approved | LUIS CCAMACHO |
| Reinforced Concrete Frame | 1/31/2025 | Approved | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV No Gas | LUIS CCAMACHO |
| Smoke Detectors | 1/31/2025 | Approved | LUIS CCAMACHO |