21121 W VANOWEN ST 91303

Certificate Information: 21121 W VANOWEN ST 91303

Application / Permit
24016-10000-05889
Plan Check / Job No.
B24LA03315
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ED1 Homekey Project. Renovation of an existing 7-story (with 1 level subterranean garage) Apartment. Scope includes interior non-structural repair, renovation of units to 11% mobility units and 4% communication unitsPROJECT HOMEKEY - MULTI-FAMILY HOUSING PER GCS 50675.1.3.
Permit Issued
Issued on 9/12/2024
Issuing Office
Current Status
Permit Finaled on 12/17/2025

Permit Application Status History

Submitted 2/29/2024 APPLICANT
Assigned to Plan Check Engineer 2/29/2024 KEVIN MORALES
Corrections Issued 3/6/2024 KEVIN MORALES
Quality Review Completed 3/7/2024 EUGENE BARBEAU
Applicant returned to address corrections 8/30/2024 KEVIN MORALES
Plan Check Approved 9/10/2024 KEVIN MORALES
Issued 9/12/2024 APPLICANT
Permit Finaled 12/16/2025 BRIAN KELLY

Permit Application Clearance Information

Density Bonus Cleared 3/14/2024 MARITES CUNANAN
Miscellaneous Cleared 3/19/2024 BRENNEN OBETO
City owned building/parcel Cleared 3/26/2024 KEVIN MORALES
Specific Plan Cleared 3/26/2024 SHEILA AHORAIAN
Green Code Cleared 4/14/2024 Rodolfo Arias
Fire Marshal Fire Life Safety Cleared 8/22/2024 MENOA AGHAJANI
DAS Clearance Cleared 9/3/2024 Rodolfo Arias
Public Housing Cleared 9/5/2024 LUIS ALVAREZ

Contact Information

Architect Maffris,, Kevin M; Lic. No.: NA33104       ,
Contractor Walton Construction Inc; Lic. No.: 1034491-B 358 E FOOTHILL BLVD STE 100      SAN DIMAS, CA 91773

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/21/2024 Partial Inspection BRIAN KELLY
Pre-Inspection 10/29/2024 Partial Inspection DEANDRE HOFFMAN
Wood Frame 1/14/2025 Not Ready for Inspection BRIAN KELLY
Wood Frame 1/17/2025 Partial Approval BRIAN KELLY
Drywall Nailing 1/22/2025 Approved BRIAN KELLY
Wood Frame 3/28/2025 Partial Inspection BRIAN KELLY
Wood Frame 4/11/2025 Partial Approval BRIAN KELLY
Drywall Nailing 4/14/2025 Not Ready for Inspection BRIAN KELLY
Drywall Nailing 4/16/2025 Partial Approval BRIAN KELLY
Drywall Nailing 4/18/2025 Partial Approval BRIAN KELLY
Drywall Nailing 4/21/2025 Partial Approval BRIAN KELLY
Interior/Exterior Lathing 5/21/2025 Partial Inspection BRIAN KELLY
Deputy Drilled-In Anchors 5/23/2025 Conditional Approval BRIAN KELLY
Deputy Drilled-In Anchors 5/29/2025 Conditional Approval BRIAN KELLY
Light Gage Steel Frame 6/25/2025 Partial Approval DEANDRE HOFFMAN
Light Gage Steel Frame 6/27/2025 Partial Approval BRIAN KELLY
Drywall Nailing 6/30/2025 Partial Approval BRIAN KELLY
Light Gage Steel Frame 7/18/2025 Partial Inspection BRIAN KELLY
Structural Steel Frame 8/7/2025 Corrections Issued BRIAN KELLY
Light Gage Steel Frame 9/8/2025 Partial Inspection BRIAN KELLY
Drywall Nailing 9/17/2025 Partial Inspection BRIAN KELLY
Light Gage Steel Frame 9/24/2025 Conditional Approval BRIAN KELLY
Light Gage Steel Frame 10/2/2025 Partial Approval BRIAN KELLY
Drywall Nailing 10/3/2025 Approved BRIAN KELLY
Final 12/10/2025 Partial Inspection BRIAN KELLY
Green Building Final 12/10/2025 Partial Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 12/10/2025 SGSOV Approved BRIAN KELLY
Smoke Detectors 12/10/2025 Approved BRIAN KELLY
Drywall Nailing 12/11/2025 Approved BRIAN KELLY
Final 12/11/2025 Partial Inspection BRIAN KELLY
Green Building Final 12/11/2025 Partial Inspection BRIAN KELLY
Final 12/16/2025 Permit Finaled BRIAN KELLY
Green Building Final 12/16/2025 Approved BRIAN KELLY