6319 1/2 W COLGATE AVE 90048

Certificate Information: 6319 1/2 W COLGATE AVE 90048

Application / Permit
24016-10000-05815
Plan Check / Job No.
B24LA03241
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 7/15/2024
Issuing Office
Current Status
CofO Issued on 11/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/22/2024 APPLICANT
Assigned to Plan Check Engineer 2/26/2024 MIROOSH KHACHATOORIAN
Corrections Issued 2/27/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 7/12/2024 ALEC MOUSAKHANIAN
Issued 7/15/2024 APPLICANT
CofO in Progress 10/31/2025 EVAN COOPER
Permit Finaled 11/4/2025 RICHARD STEINBACH
CofO Issued 11/4/2025 RICHARD STEINBACH
Permit Finaled 11/4/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/5/2024 WALLIE JONG
Sewer availability Cleared 3/5/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/6/2024 WALLIE JONG
Tenant Habitability Plan Cleared 3/12/2024 HUGO GARRIDO GARZA
Construction near power lines Cleared 7/7/2024 RIDWAN HARDY
Construction within easement Cleared 7/7/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/10/2024 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/13/2024 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 9/17/2024 Approved ARAM AVEDISIAN
Sewer 10/22/2024 Corrections Issued MEL KHACHATOURIAN
PLUMBING-Rough 10/29/2024 Partial Approval MEL KHACHATOURIAN
Insulation 12/5/2024 Partial Approval REGINA MENDEZ
BUILDING-Rough-Frame 1/16/2025 Partial Approval EVAN COOPER
ELECTRICAL-Rough 1/16/2025 Approved EVAN COOPER
Green Building Rough 1/16/2025 Not Ready for Inspection EVAN COOPER
HVAC-Rough 1/16/2025 Corrections Issued EVAN COOPER
METHANE-Rough 1/16/2025 Approved EVAN COOPER
HVAC-Rough 1/27/2025 Not Ready for Inspection MEL KHACHATOURIAN
Insulation 1/27/2025 Not Ready for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 1/27/2025 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 2/4/2025 Approved ARAM AVEDISIAN
Green Building Rough 2/4/2025 Approved ARAM AVEDISIAN
HVAC-Rough 2/4/2025 Approved ARAM AVEDISIAN
Insulation 2/4/2025 Corrections Issued ARAM AVEDISIAN
Interior/Exterior Lathing 2/4/2025 Partial Approval ARAM AVEDISIAN
Insulation 2/19/2025 Approved ARAM AVEDISIAN
Drywall Nailing 2/20/2025 Approved MEL KHACHATOURIAN
Special/Order Compliance 7/24/2025 Approved EVAN COOPER
ELECTRICAL-Final 8/29/2025 Approved EVAN COOPER
Final 8/29/2025 Corrections Issued EVAN COOPER
Green Building Final 8/29/2025 Approved EVAN COOPER
HVAC-Final 8/29/2025 Approved EVAN COOPER
PLUMBING-Final 8/29/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 8/29/2025 Approved EVAN COOPER
Final 10/30/2025 OK to Issue CofO EVAN COOPER