6319 1/2 W COLGATE AVE 90048
Certificate Information: 6319 1/2 W COLGATE AVE 90048
- Application / Permit
- 24016-10000-05815
- Plan Check / Job No.
- B24LA03241
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 7/15/2024
- Issuing Office
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 2/27/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 7/12/2024 | ALEC MOUSAKHANIAN |
| Issued | 7/15/2024 | APPLICANT |
| CofO in Progress | 10/31/2025 | EVAN COOPER |
| Permit Finaled | 11/4/2025 | RICHARD STEINBACH |
| CofO Issued | 11/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/5/2024 | WALLIE JONG |
| Sewer availability | Cleared | 3/5/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2024 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 3/12/2024 | HUGO GARRIDO GARZA |
| Construction near power lines | Cleared | 7/7/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/7/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/10/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 9/13/2024 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 9/17/2024 | Approved | ARAM AVEDISIAN |
| Sewer | 10/22/2024 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 10/29/2024 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 12/5/2024 | Partial Approval | REGINA MENDEZ |
| BUILDING-Rough-Frame | 1/16/2025 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 1/16/2025 | Approved | EVAN COOPER |
| Green Building Rough | 1/16/2025 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 1/16/2025 | Corrections Issued | EVAN COOPER |
| METHANE-Rough | 1/16/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 1/27/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Insulation | 1/27/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 1/27/2025 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 2/4/2025 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 2/4/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 2/4/2025 | Approved | ARAM AVEDISIAN |
| Insulation | 2/4/2025 | Corrections Issued | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/4/2025 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 2/19/2025 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 2/20/2025 | Approved | MEL KHACHATOURIAN |
| Special/Order Compliance | 7/24/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/29/2025 | Approved | EVAN COOPER |
| Final | 8/29/2025 | Corrections Issued | EVAN COOPER |
| Green Building Final | 8/29/2025 | Approved | EVAN COOPER |
| HVAC-Final | 8/29/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/29/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 8/29/2025 | Approved | EVAN COOPER |
| Final | 10/30/2025 | OK to Issue CofO | EVAN COOPER |