1200 W 7TH ST 7th Floor 90017
Certificate Information: 1200 W 7TH ST 7th Floor 90017
- Application / Permit
- 24016-10000-05762
- Plan Check / Job No.
- B24LA03213
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- EPLAN Office T.I. including new non-load bearing partitions, ceiling, finishes and millwork. Structural support for movable partitions, New elevator lobby access controls , all work per engineering
- Permit Issued
- Issued on 1/13/2025
- Issuing Office
- Current Status
- Permit Finaled on 10/31/2025
Permit Application Status History
| Submitted | 2/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/29/2024 | RARES BODEA |
| Assigned to Zoning Architect | 2/29/2024 | RARES BODEA |
| Corrections Issued | 3/4/2024 | RARES BODEA |
| Quality Review Completed | 3/8/2024 | STEVEN KIM |
| Applicant returned to address corrections | 4/19/2024 | RARES BODEA |
| Applicant returned to address corrections | 5/29/2024 | RARES BODEA |
| Plan Check Approved | 5/30/2024 | RARES BODEA |
| Issued | 1/13/2025 | APPLICANT |
| Permit Finaled | 10/31/2025 | PAUL BAZERKANIAN |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/19/2024 | YI LU |
| ZI | Cleared | 3/19/2024 | YI LU |
| Green Code | Cleared | 4/25/2024 | AARON COSTA |
| DAS Clearance | Cleared | 5/8/2024 | Rosendo Medina |
| Fire Marshal Fire Life Safety | Cleared | 5/21/2024 | FIRE DEPARTMENT |
| Zoning Plan Check | Cleared | 5/30/2024 | Rosendo Medina |
Contact Information
| Architect | Stewart,, Kirk Jeffrey; Lic. No.: C33107 | 830 PALLADIUM BLVD PALM SPRINGS, CA 92262 |
| Contractor | S P C Industries Inc; Lic. No.: 433163-B | , |
| Contractor | Sierra Pacific Constructors Inc; Lic. No.: 433163-B | , |
| Engineer | Caravalho,, Kim; Lic. No.: S4896 | 541 LINWOOD AVENUE UNIT A MONROVIA, CA 91016 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 4/21/2025 | Partial Approval | JEROME BLACKWOOD |
| Structural Steel Frame | 4/21/2025 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 4/25/2025 | Partial Approval | PAUL BAZERKANIAN |
| Structural Steel Frame | 4/30/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 5/1/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 6/12/2025 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 7/2/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 7/15/2025 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 7/15/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 7/18/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 7/21/2025 | Partial Approval | PAUL BAZERKANIAN |
| T-Bar Ceiling | 9/2/2025 | Partial Approval | PAUL BAZERKANIAN |
| T-Bar Ceiling | 9/30/2025 | Partial Approval | PAUL BAZERKANIAN |
| Final | 10/31/2025 | Permit Finaled | PAUL BAZERKANIAN |
| Green Building Final | 10/31/2025 | Approved | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Approved | PAUL BAZERKANIAN |
| Smoke Detectors | 10/31/2025 | Approved | PAUL BAZERKANIAN |