5437 S WEST BLVD 90043

Certificate Information: 5437 S WEST BLVD 90043

Application / Permit
24016-10000-05757
Plan Check / Job No.
B24LA03209
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) STORAGE TO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 5/17/2024
Issuing Office
Current Status
CofO Issued on 2/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2024 APPLICANT
Assigned to Plan Check Engineer 2/27/2024 GIOVANNY CHAVEZ
Corrections Issued 2/28/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 3/19/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 5/10/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 5/14/2024 GIOVANNY CHAVEZ
Plan Check Approved 5/16/2024 GIOVANNY CHAVEZ
Issued 5/17/2024 APPLICANT
CofO in Progress 1/29/2025 LUIS CASTRO
Permit Finaled 2/9/2025 DEROLD HAUFF
CofO Issued 2/9/2025 DEROLD HAUFF
Permit Finaled 2/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/28/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 2/28/2024 JESSICA OPINION
Sewer availability Cleared 2/28/2024 JESSICA OPINION
Construction near power lines Cleared 5/9/2024 RIDWAN HARDY
Construction within easement Cleared 5/9/2024 RIDWAN HARDY

Contact Information

Contractor Proud Crowd Inc The; Lic. No.: 1074719-B       ,
Engineer Aronianpour,, Eilan; Lic. No.: NA88101       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/24/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 5/24/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 5/29/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Partial Approval ANTHONY EGSON
Sewer 9/4/2024 Approved ANTHONY EGSON
Underground Mechanical 9/4/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 9/18/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 9/18/2024 Approved AMIR NAZARIAN
Green Building Rough 9/18/2024 Not Ready for Inspection AMIR NAZARIAN
HVAC-Rough 9/18/2024 Not Ready for Inspection AMIR NAZARIAN
PLUMBING-Rough 9/18/2024 Approved AMIR NAZARIAN
Service/Power Release 9/19/2024 Partial Inspection ANTHONY EGSON
BUILDING-Rough-Frame 10/10/2024 Approved ANTHONY EGSON
Green Building Rough 10/10/2024 Approved ANTHONY EGSON
HVAC-Rough 10/10/2024 Approved ANTHONY EGSON
Insulation 10/17/2024 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 10/17/2024 Approved ANTHONY EGSON
Insulation 10/22/2024 Approved JOSH MEISTER
Drywall Nailing 10/29/2024 Approved ALEX COLIN
Final 12/16/2024 Not Ready for Inspection BARRY HACHE
Green Building Final 12/16/2024 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Approved BARRY HACHE
Service/Power Release 12/16/2024 Corrections Issued BARRY HACHE
Smoke Detectors 12/16/2024 Approved BARRY HACHE
Final 12/23/2024 Corrections Issued LUIS CASTRO
Green Building Final 12/23/2024 Not Ready for Inspection LUIS CASTRO
Service/Power Release 12/23/2024 Approved LUIS CASTRO
Final 1/22/2025 Partial Approval LUIS CASTRO
Green Building Final 1/22/2025 Approved LUIS CASTRO
Final 1/29/2025 OK to Issue CofO LUIS CASTRO