5437 S WEST BLVD 90043
Certificate Information: 5437 S WEST BLVD 90043
- Application / Permit
- 24016-10000-05757
- Plan Check / Job No.
- B24LA03209
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) STORAGE TO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 5/17/2024
- Issuing Office
- Current Status
- CofO Issued on 2/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 2/28/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 3/19/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 5/10/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 5/14/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 5/16/2024 | GIOVANNY CHAVEZ |
| Issued | 5/17/2024 | APPLICANT |
| CofO in Progress | 1/29/2025 | LUIS CASTRO |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
| CofO Issued | 2/9/2025 | DEROLD HAUFF |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 2/28/2024 | JESSICA OPINION |
| Construction near power lines | Cleared | 5/9/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Proud Crowd Inc The; Lic. No.: 1074719-B | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: NA88101 | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/24/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/24/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/29/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2024 | Partial Approval | ANTHONY EGSON |
| Sewer | 9/4/2024 | Approved | ANTHONY EGSON |
| Underground Mechanical | 9/4/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 9/18/2024 | Approved | AMIR NAZARIAN |
| Green Building Rough | 9/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Rough | 9/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| PLUMBING-Rough | 9/18/2024 | Approved | AMIR NAZARIAN |
| Service/Power Release | 9/19/2024 | Partial Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/10/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/10/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 10/10/2024 | Approved | ANTHONY EGSON |
| Insulation | 10/17/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/17/2024 | Approved | ANTHONY EGSON |
| Insulation | 10/22/2024 | Approved | JOSH MEISTER |
| Drywall Nailing | 10/29/2024 | Approved | ALEX COLIN |
| Final | 12/16/2024 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 12/16/2024 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 12/16/2024 | SGSOV Approved | BARRY HACHE |
| Service/Power Release | 12/16/2024 | Corrections Issued | BARRY HACHE |
| Smoke Detectors | 12/16/2024 | Approved | BARRY HACHE |
| Final | 12/23/2024 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 12/23/2024 | Not Ready for Inspection | LUIS CASTRO |
| Service/Power Release | 12/23/2024 | Approved | LUIS CASTRO |
| Final | 1/22/2025 | Partial Approval | LUIS CASTRO |
| Green Building Final | 1/22/2025 | Approved | LUIS CASTRO |
| Final | 1/29/2025 | OK to Issue CofO | LUIS CASTRO |