3504 W 8TH ST B 90005

Certificate Information: 3504 W 8TH ST B 90005

Application / Permit
24016-10000-05695
Plan Check / Job No.
B24LA03171
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE OF USE FROM Medical Office TO RESTAURANT "ALCOHOL SALES/SERVICE PROHIBITED"
Permit Issued
Issued on 2/14/2025
Issuing Office
Metro
Current Status
CofO Corrected on 11/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2024 APPLICANT
Assigned to Plan Check Engineer 2/26/2024 FERNANDO FLORES
Corrections Issued 2/27/2024 FERNANDO FLORES
Plan Check Approved 2/11/2025 TSE MING HUANG
Issued 2/14/2025 APPLICANT
CofO Issued-Status Void 9/8/2025 RAFAEL ESPINOZA
Permit Finaled-Status Void 9/8/2025 RAFAEL ESPINOZA
Re-Activate Permit 11/26/2025 ERNESTO CORRAL
Permit Finaled 11/26/2025 ERNESTO CORRAL
CofO Corrected 11/26/2025 ERNESTO CORRAL
Permit Finaled 11/26/2025 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/19/2024 JEANIE LAM
"Q" conditions Cleared 7/23/2024 DAVID URITA
"T" removal Cleared 7/23/2024 DAVID URITA
Food Service Establishment Cleared 8/13/2024 PAWAN VERMA
Sewer availability Cleared 8/26/2024 JUSTIN BICOL
ZA Case Cleared 11/27/2024 GRACIELA ACOSTA
Historic Resource Verification Cleared 12/3/2024 YASMINE BASHIRI
Redevelopment Project Area Cleared 12/3/2024 YASMINE BASHIRI
Food establishment approval Cleared 1/16/2025 LACDHS APPROVED

Contact Information

Contractor Yoo Sung Kun; Lic. No.: 1001698-B 3119 EL CAMINITO      LA CRESCENTA, CA 91214
Engineer Kim,, Hosang; Lic. No.: C67288 18759 WILLOWTREE LANE      PORTER RANCH, CA 91326

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/12/2025 Partial Inspection JEROME BLACKWOOD
Wood Frame 4/21/2025 Partial Approval JEROME BLACKWOOD
Footing/Foundation/Slab 4/22/2025 Partial Approval JEROME BLACKWOOD
Drywall Nailing 5/2/2025 Partial Approval JEROME BLACKWOOD
T-Bar Ceiling 5/2/2025 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 5/2/2025 Approved JEROME BLACKWOOD
Drywall Nailing 5/13/2025 Partial Approval JEROME BLACKWOOD
T-Bar Ceiling 5/13/2025 Not Ready for Inspection JEROME BLACKWOOD
T-Bar Ceiling 5/28/2025 Approved JEROME BLACKWOOD
Final 7/29/2025 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 7/29/2025 Approved JEROME BLACKWOOD
Final 8/11/2025 Partial Approval PAUL BAZERKANIAN