6200 W WILSHIRE BLVD 90048

Certificate Information: 6200 W WILSHIRE BLVD 90048

Application / Permit
24016-10000-05237
Plan Check / Job No.
B24LA02927
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePlan SEISMIC RETROFIT TO EXISTING 16 STORY, TYPE 1 BUILDING. SCOPE OF WORK INCLUDES SEISMIC RENOVATION OF AN EXISTING CONCRETE BUILDING PER NDC ORDINANCE AND MINOR DEMOLITION.
Permit Issued
Issued on 7/2/2025
Issuing Office
Current Status
Issued on 7/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/20/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 FARSHAD ALIMOHAMADI
Corrections Issued 3/11/2024 FARSHAD ALIMOHAMADI
Quality Review Completed 3/18/2024 HAMID REZAEI
Applicant returned to address corrections 4/4/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 4/5/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 5/20/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/16/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 6/20/2025 FARSHAD ALIMOHAMADI
Issued 7/2/2025 APPLICANT

Permit Application Clearance Information

"Q" conditions Cleared 4/2/2025 NATHAN ROMINE
Green Code Cleared 4/18/2025 FARSHAD ALIMOHAMADI
Metro Rail approval Cleared 4/23/2025 JENNIFER SU
Fire Marshal Fire Life Safety Cleared 5/23/2025 PEJMAN NOORI
DAS Clearance Cleared 6/13/2025 CAROLYNN NEPOMUCENO

Contact Information

Architect Lagrega,, Gregory Thomas; Lic. No.: C31444 2769 WRIGHT LANE      LOS ANGELES, CA 90068
Contractor Owner-Builder       ,
Engineer Ghodsi,, Afshin; Lic. No.: S3248 888 S FIGUEROA ST 18TH FLOOR      LOS ANGELES, CA 90017

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/13/2025 Corrections Issued DARRYL ARNOLD
Green Building Rough 9/29/2025 Approved DARRYL ARNOLD
METHANE-Rough 9/29/2025 Conditional Approval DARRYL ARNOLD
Reinforced Concrete Frame 9/29/2025 Approved DARRYL ARNOLD
METHANE-Rough 12/16/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Reinforced Concrete Frame 12/16/2025 Conditional Approval CHRISTOPHER BLACKWOOD
METHANE-Rough 12/29/2025 Conditional Approval DARRYL ARNOLD
Reinforced Concrete Frame 12/29/2025 Not Ready for Inspection DARRYL ARNOLD
METHANE-Rough 1/21/2026 Not Ready for Inspection DARRYL ARNOLD
Reinforced Concrete Frame 1/21/2026 Conditional Approval DARRYL ARNOLD
METHANE-Rough 1/28/2026 Approved CHRISTOPHER BLACKWOOD
Reinforced Concrete Frame 1/28/2026 Partial Approval CHRISTOPHER BLACKWOOD
Floor/Roof Diaphrgm/Shear Wall 2/19/2026 Partial Approval MARTIN TAVITIAN
Reinforced Concrete Frame 2/19/2026 Partial Approval MARTIN TAVITIAN
Final 7/21/2026 Not Ready for Inspection MARTIN TAVITIAN
Green Building Final 7/21/2026 Approved MARTIN TAVITIAN
Reinforced Concrete Frame 7/21/2026 Not Ready for Inspection MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 7/21/2026 SGSOV Not Required MARTIN TAVITIAN
Smoke Detectors 7/21/2026 Not Ready for Inspection MARTIN TAVITIAN
Final 7/23/2026 Partial Inspection MARTIN TAVITIAN
Reinforced Concrete Frame 7/23/2026 Approved MARTIN TAVITIAN
Smoke Detectors 7/23/2026 Approved MARTIN TAVITIAN