5017 1/2 S HALLDALE AVE 90062
Certificate Information: 5017 1/2 S HALLDALE AVE 90062
- Application / Permit
- 24016-10000-04869
- Plan Check / Job No.
- B24LA02729
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **Eplan** CONVERSION OF (E) DETACHED GARAGE TO ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2024 | ALFREDO JARA |
| Corrections Issued | 3/13/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 4/5/2024 | ALFREDO JARA |
| Plan Check Approved | 5/18/2024 | EDWIN ESPIN |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 2/12/2025 | BARRY HACHE |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
| CofO Issued | 2/13/2025 | DEROLD HAUFF |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/15/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 3/15/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 3/15/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2024 | TREVOR QUAN |
| Community Plan Implem. Overlay | Cleared | 4/26/2024 | MANERI ROMAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/17/2024 | Corrections Issued | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 6/24/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 6/24/2024 | Corrections Issued | CRAIG DAVIS |
| Sewer | 6/24/2024 | Corrections Issued | CRAIG DAVIS |
| Deputy Drilled-In Anchors | 6/26/2024 | Conditional Approval | JOSH MEISTER |
| Excavation/Setback/Form/Re-Bar | 6/26/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 6/26/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Sewer | 6/26/2024 | Partial Approval | CRAIG DAVIS |
| Sewer | 6/27/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 6/27/2024 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 7/9/2024 | Approved | CRAIG DAVIS |
| Gas Test | 7/9/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 7/9/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 7/9/2024 | SGSOV Not Ready | CRAIG DAVIS |
| PLUMBING-Rough | 7/17/2024 | No Access for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 7/17/2024 | SGSOV Not Ready | DAVID FEILER |
| PLUMBING-Rough | 7/23/2024 | Approved | MICHAEL LEWIS |
| Shower Pan | 7/23/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 7/23/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/30/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/4/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Rough | 9/4/2024 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 9/4/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Rough | 9/18/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 10/2/2024 | Corrections Issued | JOHN QUINTANILLA |
| HVAC-Rough | 10/2/2024 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 10/7/2024 | Approved | CRAIG DAVIS |
| HVAC-Rough | 10/7/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Rough | 10/10/2024 | Approved | CRAIG DAVIS |
| Insulation | 10/17/2024 | Approved | RUBEN SALAS |
| Drywall Nailing | 10/22/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 11/15/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Service/Power Release | 11/15/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Service/Power Release | 11/19/2024 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Final | 11/25/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 11/25/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Final | 11/25/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 12/6/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 12/6/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/20/2024 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 12/20/2024 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | CRAIG DAVIS |
| Final | 1/29/2025 | No Access for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Not Ready | BARRY HACHE |
| Service/Power Release | 1/29/2025 | No Access for Inspection | BARRY HACHE |
| Smoke Detectors | 1/29/2025 | No Access for Inspection | BARRY HACHE |
| Final | 2/4/2025 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Approved | BARRY HACHE |
| Service/Power Release | 2/4/2025 | Not Ready for Inspection | BARRY HACHE |
| Smoke Detectors | 2/4/2025 | Corrections Issued | BARRY HACHE |
| Final | 2/11/2025 | OK to Issue CofO | BARRY HACHE |
| Service/Power Release | 2/11/2025 | Approved | BARRY HACHE |
| Smoke Detectors | 2/11/2025 | Approved | BARRY HACHE |